Installation instructions Logamax plus GB162-80/100 cascade unit • Version 01/2006

Cascade frame installation

4

4.1

Boiler assembly and pump group 
installation

z

Hang the first boiler on the cascade frame as shown in fig. 7 
or fig. 8.

z

Put the boiler in the correct position and level it horizontally 
and vertically. Use the set screws on the lower rear of the 
boiler to adjust it.

z

Connect the pump group (see Logamax plus GB162 Instal-
lation and service instructions).

z

Remove the protective yellow caps from the main gas pipe.

z

Apply PTFE tape to the screw thread connections.

z

Connect up the gas connection pipe between the gas valve 
and the main gas pipe. Use PTFE tape to create a perfect 
seal.

z

Remove the protective caps from the header.

z

Remove all red paint and unevenness from the flow and 
return connections of the header.

z

Install the flow pipe(s) between the header and the pump 
group.

z

Install the return pipe(s) between the header and the pump 
group.

z

Repeat the above steps to install all boilers.

z

If required, seal off any unused connections of the main gas 
pipe and the header.

z

Install the condensate drain pipe. Use the pre-assembled 
mounting brackets on the supports for this.

z

When installing a cascade with an angled low loss header, 
install the set of bends between the header and the low loss 
header. Fit the enclosed flange seals in between. Use the 
corresponding screws.
– 2½" low loss header 

M12 x 50

– 3" low loss header

M16 x 55

z

Install the low loss header with the corresponding flange 
seals. Use the corresponding screws.
– 2½" low loss header 

M12 x 50

– 3" low loss header 

M16 x 55

Fig. 7

Installation sequence for a TL-inline configuration

1

2

3

Note!

You must observe the installation sequence 
indicated in fig. 7 and fig. 8 when installing the 
boilers.

Fig. 8

Installation sequence for TR-back-to-back 
configuration

1

3

5

2

4

6

Caution!

– Do not install the pump group cover until 

pressure has been supplied to the boiler 
system and the gas pipe.

– Check the cascade system for leaks.

Содержание GB162-80

Страница 1: ...Please read thoroughly before starting installation 7217 5800 01 2006 GB EN For heating engineers Installation instructions Logamax plus GB162 80 100 cascade unit...

Страница 2: ...Supports Item 2 Connecting frame Item 3 Main gas pipe Item 4 Flow and return header Item 5 Gas connection kit TL inline Item 6 Mounting bracket Item 7 Boiler connection set TL inline Item 8 Boiler co...

Страница 3: ...l co uk Installation instructions Logamax plus GB162 80 100 cascade unit Version 01 2006 List of contents 1 General points 4 2 Items supplied with unit 4 3 Dimensions 6 4 Cascade frame installation 8...

Страница 4: ...vidual cascade frame parts enable simple and quick installation 2 Items supplied with unit Cascade frame fig 1 Supports Connecting frame Main gas pipe Flow and return header Boiler connection kit Flan...

Страница 5: ...ous configurations fig 4 By using the bend set the low loss header can be installed at an angle to the boilers The gas pipe is reversible so that the gas connection can be at the other side of the boi...

Страница 6: ...01 2006 Dimensions 3 3 Dimensions Fig 5 Dimensions of cascade systems 1 Item A TL inline configuration Item B TR back to back installation Item 1 Flow and return header Item 2 Low loss header with ben...

Страница 7: ...L3 1625 38 1663 575 TL4 2150 42 2192 575 TL5 2675 45 2720 575 TL6 3200 45 3245 575 TL7 3725 45 3770 575 TL8 4250 45 4295 575 Table 4 TL inline configurations Cascade system Header inch Length mm B1 mm...

Страница 8: ...main gas pipe Use the M8 x 70 screws for this Do not fully tighten the screws yet z Install the header pipe Use the M8 x 70 screws for this Do not fully tighten the screws yet z Fit the boiler mounti...

Страница 9: ...pipe s between the header and the pump group z Install the return pipe s between the header and the pump group z Repeat the above steps to install all boilers z If required seal off any unused connec...

Страница 10: ...trim the insulation so that it is straight fig 9 item 3 z For 2 and 3 low loss header install the inserts in the outer insulation For a 2 low loss header install the redu cing inserts in the outer rec...

Страница 11: ...11 We reserve the right to make technical modifications W http www buderus commercial co uk Installation instructions Logamax plus GB162 80 100 cascade unit Version 01 2006 Notes...

Страница 12: ...Commercial Fax 01905 75 31 30 www buderus commercial co uk In the UK Buderus is a trading name of BBT Thermotechnology Ltd C F Quadrant Ltd Unit L40 Cherry Orchard Industrial Estate Cherry Orchard Dub...

Отзывы: