Installation instructions Logamax plus GB162-80/100 cascade unit • Version 01/2006

Cascade frame installation

4

4

Cascade frame installation

z

Fix the frame onto the first leg of the cascade unit. 
Use the M8 x 70 screws for this.

z

Now fix the next leg and continue fitting until the cascade 
unit is compelte.

z

Position the frame into its final position.

z

Adjust the frame so that it is in the right position and so that 
it is level both horizontally and vertically. Fit additional 
washers under the leg until level.

z

Secure the frame to the floor. Ensure bolts are aligned to the 
legs. Do not bend or place the leg under stress to make it fit.

z

Install the main gas pipe. Use the M8 x 70 screws for this. 
Do not fully tighten the screws yet.

z

Install the header pipe. Use the M8 x 70 screws for this. 
Do not fully tighten the screws yet.

z

Fit the boiler mounting brackets on the top of the frame. 
Install the nuts at the rear of the frame. The underside of the 
bracket should be level with the underside of the frame. 
Use the M8 x 65 screws for this.

Caution!

– Make sure that the surface the cascade 

system is to be installed on is flat. 

– Use a spirit level when installing the cascade 

system.

– Check that the load-bearing capacity of the 

floor is sufficient for the weight of the installa-
tion (approx. 100 kg for each boiler with 
accessories).

Caution!

Make sure that the slots for the boiler mounting 
bracket are at the top of the frame.

Caution!

For TR-back-to-back configurations, both boiler 
mounting brackets are fitted simultaneously, 
using the same screws. Only use M8 x 65 
screws to secure the mounting brackets.

Содержание GB162-80

Страница 1: ...Please read thoroughly before starting installation 7217 5800 01 2006 GB EN For heating engineers Installation instructions Logamax plus GB162 80 100 cascade unit...

Страница 2: ...Supports Item 2 Connecting frame Item 3 Main gas pipe Item 4 Flow and return header Item 5 Gas connection kit TL inline Item 6 Mounting bracket Item 7 Boiler connection set TL inline Item 8 Boiler co...

Страница 3: ...l co uk Installation instructions Logamax plus GB162 80 100 cascade unit Version 01 2006 List of contents 1 General points 4 2 Items supplied with unit 4 3 Dimensions 6 4 Cascade frame installation 8...

Страница 4: ...vidual cascade frame parts enable simple and quick installation 2 Items supplied with unit Cascade frame fig 1 Supports Connecting frame Main gas pipe Flow and return header Boiler connection kit Flan...

Страница 5: ...ous configurations fig 4 By using the bend set the low loss header can be installed at an angle to the boilers The gas pipe is reversible so that the gas connection can be at the other side of the boi...

Страница 6: ...01 2006 Dimensions 3 3 Dimensions Fig 5 Dimensions of cascade systems 1 Item A TL inline configuration Item B TR back to back installation Item 1 Flow and return header Item 2 Low loss header with ben...

Страница 7: ...L3 1625 38 1663 575 TL4 2150 42 2192 575 TL5 2675 45 2720 575 TL6 3200 45 3245 575 TL7 3725 45 3770 575 TL8 4250 45 4295 575 Table 4 TL inline configurations Cascade system Header inch Length mm B1 mm...

Страница 8: ...main gas pipe Use the M8 x 70 screws for this Do not fully tighten the screws yet z Install the header pipe Use the M8 x 70 screws for this Do not fully tighten the screws yet z Fit the boiler mounti...

Страница 9: ...pipe s between the header and the pump group z Install the return pipe s between the header and the pump group z Repeat the above steps to install all boilers z If required seal off any unused connec...

Страница 10: ...trim the insulation so that it is straight fig 9 item 3 z For 2 and 3 low loss header install the inserts in the outer insulation For a 2 low loss header install the redu cing inserts in the outer rec...

Страница 11: ...11 We reserve the right to make technical modifications W http www buderus commercial co uk Installation instructions Logamax plus GB162 80 100 cascade unit Version 01 2006 Notes...

Страница 12: ...Commercial Fax 01905 75 31 30 www buderus commercial co uk In the UK Buderus is a trading name of BBT Thermotechnology Ltd C F Quadrant Ltd Unit L40 Cherry Orchard Industrial Estate Cherry Orchard Dub...

Отзывы: