![Brooks Polycold MaxCool 2500L Скачать руководство пользователя страница 84](http://html1.mh-extra.com/html/brooks/polycold-maxcool-2500l/polycold-maxcool-2500l_installation-and-operation-manual_2818694084.webp)
Installation
Polycold Cryochiller
Check the Refrigerant Line and Cryosurface for Leaks
Installation and Operation Manual
Brooks Automation
4-28
214072 Revision B
sure. This is important to assure that helium does not migrate into and contaminate the refrigerant sys-
tem. When the system is off, the lowest pressure is the balance pressure.
During evacuation of the line and coil, after the leak check, it is recommended to purge the line with dry
nitrogen or dry argon that has a dew point of -80 C or less since it can be difficult to pump out pure
helium.
Be aware of false positives created by the armaflex insulation around the line set. The factory installed
tube insulation and flat insulation can produce false positives with some leak check sensors.
Leak Check Procedure
Refer to
and
for the following steps.
1.
Make certain the valves on the manifold are closed.
2.
Connect the manifold's suction (low pressure) hose to the evacuation valve inside the valve box.
See
.
3.
Open the evacuation valve.
4.
Connect the refrigerant cylinder to the center port of the manifold.
5.
Open the suction valve on the manifold and pressurize the refrigerant line and cryosurface to
70-140 kPa (10-20 psig). This adds refrigerant trace gas to the system.
Figure 4-21: Leak Check - Add “Trace” Refrigerant
Refrigerant
Gas
R134a
Dry
Nitrogen
Gas