Section 2

Transit Precautions 

To safeguard against damage during transit, transport the instrument to the 

installation site in the same container used for transportation from the factory 

if circumstances permit.

Installation

A. Location

For proper operation of the GT1600 flowmeter it must be mounted within

6 degrees of true vertical, with the inlet connection at the bottom of the

meter, and the outlet at the top. The use of a plumb-bob, level or other

device to assure vertical positioning is recommended.

B. Piping Arrangement

It is strongly recommended that the typical piping arrangement shown in

Figure 2-1, be used when installing the meter. This piping arrangement

permits the meter to be isolated from the flow for servicing or cleaning.

The design of the GT1600 flowmeter allows the horizontal inlet and outlet

end fitting to rotate independently of each other simply by loosening the

two clamp bolts for each end fitting at the rear of the meter. Additionally

the various end fittings offer horizontal or vertical connections or a

combination of both.

Figure 2-1 Typical Flowmeter Piping Configuration

A - Inlet Valve

B - O utlet Valve

C - Bypass Valve

D - Control Valve

E - Drain Valve

HO RIZO NTAL

LINE

D

A

E

C

VERTICAL

LINE

B

B

A

E

FLO W M ETER

C

D

FLO W M ETER

18

Содержание GT1600

Страница 1: ...Installation and Operation Manual X VA GT1600 eng Part Number 541B220AAG April 2020 GT1600 Series Brooks GT1600 Industrial Glass Tube Variable Area Flowmeter GT1600 Series...

Страница 2: ...r electrical and pressure sources Operation 1 Slowly initiate flow into the system Open process valves slowly to avoid flow surges 2 Check for leaks around the flow meter inlet and outlet connections...

Страница 3: ...n manual Failure to comply could result in serious personal injury or property damage Protective sleeve must remain over glass tube Meter sizes 7 10 only Fasten meter windows securely Failure to compl...

Страница 4: ...lation General 17 Receipt of Equipment 17 Recommended Storage Practice 17 Return Shipment 17 Transit Precautions 18 Installation 18 Section 3 Operation Pre Operational Check 19 Operating Instructions...

Страница 5: ...ches for GT1600 Sizes 2 6 15 1 7 Dimensions and Specifications Intrinsically Safe Switch Isolators 16 2 1 Typical Flowmeter Piping Configuration 18 3 1 Typical Flowmeter Piping Configuration 20s 5 1 G...

Страница 6: ...peration The operating parts of the flowmeter consist of a tapered glass tube and a float which operates within the tube The fluid enters the bottom of the tube which has the smallest inside diameter...

Страница 7: ...ting in the center of the tube The guide ribs do not follow the taper of the tube They are parallel to the tube centerline so that the proper operating clearance for the float is maintained for its en...

Страница 8: ...ure Ratings Float wetted Materials of construction Maximum Operating Pressure PSIG bar at Max Operating Temperature Tube size Threaded process connections Flanged process connections Horizontal IN OUT...

Страница 9: ...S 23 A 0 66 150 2 7 4 6 8 XV 8 A 0 99 220 4 6 9 8 XV 14 A 1 3 310 5 3 9 1 8 XV 31 A 1 7 400 11 20 9 XS 33 A 3 0 690 12 21 9 XV 87 A 3 6 830 26 44 9 XS 87 A 4 5 1000 32 55 10 XV64 A 6 1300 24 41 10 XS...

Страница 10: ...Section 1 Figure 1 4 Dimensions GT1600 Series See Dimensions Tables on following pages 5...

Страница 11: ...N H OUT 9 1 4 0 72 120 0 V IN V OUT 1024 19 69 500 0 H IN V OUT 7 8 3 94 100 0 H IN V OUT 9 1 4 0 72 120 0 V IN H OUT 7 3 8 94 100 0 V IN H OUT 9 10 4 72 120 0 H IN H OUT 7 22 88 8 3 50 88 9 H IN H OU...

Страница 12: ...H OUT 9 10 15 00 381 0 4 00 101 6 H IN H OUT 9 02 229 1 0 83 21 0 V IN V OUT 11 20 284 6 H IN V OUT 10 11 256 9 0 83 21 0 V IN H OUT 10 11 256 9 0 83 21 0 V IN V OUT Retro t only 4 GT1305 1305 7 75 1...

Страница 13: ...v 1 Groups A thru G Ex mb IIC T6 Gb Ex mb IIIC T85 C Db Standard Version KIWA 18ATEX0013 X IECEx KIWA 18 0008X Declarations Mark Meter Options Standards Directives Marking Status Certificate Explosion...

Страница 14: ...ipment depends not on the equipment itself but on operating conditions of the process uid gas owing through the equipment The equipment by itself does not generate heat Due to this reason the temperat...

Страница 15: ...nsists of a biasing magnet and hermetically sealed reed switch which is insulated to prevent damage from mild shock and normal pipe vibration The contact rating of the switch is very low 0 5A An exter...

Страница 16: ...t have a breaking capacity in accordance with the prospective short circuit current of the circuit to properly break the systems highest short circuit current In case device is mounted in an area wher...

Страница 17: ...ically safe circuits An additional external connection facility for an equipotential bonding conductor is provided on the metallic enclosure The product should be installed by suitably trained personn...

Страница 18: ...Section 1 13 Figure 1 5 Reed Switch Alarm UL Installation...

Страница 19: ...tacts may be made to operate simultaneously For hazardous area applications Brooks can supply an approved Namur power supply amplifier relay unit to obtain an intrinsic safe current circuit Please ref...

Страница 20: ...type of valve can cause pressure shocks which can damage the glass tube GT1600 Alarm Contact Bistabble Inductive Switches Meter Size 2 to 6 Application Electrical Equipment for use in Hazardous locat...

Страница 21: ...Section 1 Figure 1 7 Dimensions and Specs Intrinsically Safe Switch Isolators 16...

Страница 22: ...ged or missing parts Recommended Storage Practice If intermediate or long term storage of equipment is required it is recommended that the equipment be stored in accordance with the following a Within...

Страница 23: ...recommended that the typical piping arrangement shown in Figure 2 1 be used when installing the meter This piping arrangement permits the meter to be isolated from the flow for servicing or cleaning...

Страница 24: ...eference lines are not aligned loosen the screws securing the scale and move it until the marks are in alignment Then tighten the screws Operating Instructions After the flowmeter has been properly in...

Страница 25: ...H IN V OUT 9 1 1 0 7 38 441 3 V IN H OUT 7 1 8 6 75 425 5 V IN H OUT 9 10 17 38 441 3 V IN V OUT Retro t only 4 GT1307 1307 16 94 430 2 H IN H OUT 7 8 3 94 100 0 H IN H OUT 9 1 4 0 72 120 0 V IN V OUT...

Страница 26: ...Section 4 Overview 21...

Страница 27: ...e float stops float and end fittings with a suitable solvent 6 Install the inlet float stop into the metering tube Refer to Figure 1 3 for the correct orientation of the float Slide the float into the...

Страница 28: ...Section 5 General See Figures 5 1 and 5 2 and Table 5 1 for parts assembly drawings and parts list Figure 5 1 GT1600 Sizes 2 6 Parts Assembly Drawing Ref GT16XX001_1 23...

Страница 29: ...Section 5 Figure 5 2 GT1600 Sizes 7 10 Parts Assembly Drawing Ref GT16XX002_1 24...

Страница 30: ...14 TUBE SEAT GASKET PACKING 15 CENTERING RING TUBE GASKET SZ 2 6 16 SLEEVE 17 LABEL CLEAR SCALE 18 RESERVED FOR LABEL WHITE BACKING 20 CENTERING RING 21 SCREW CENTERING RING 22 WINDOW ASSEMBLY 23 SCR...

Страница 31: ...n nearest to you START UP SERVICE AND IN SITU CALIBRATION Brooks Instrument can provide start up service prior to operation when required For some process applications where ISO 9001 Quality Certifica...

Отзывы: