System Installation
15
Item Description
2
The cable shell not damaged.
3
Grounding cable is connected properly.
4
Cables are dressed neatly, power kept separate from signal.
5
The minimum bending radius of the cable is proper. (Shouldn’t be less than twenty times of the cable’s
diameter.)
2.5 System
Test
Test the system after the device was installed and inspected.
Test steps for Outdoor Booster:
VSWR testing (sweep test of cables and antenna)
Effect testing: DT/CQT testing
Region optimize: base on the OMC-R statistic data, adjusting the base station’s physical
parameter, regional parameter and switch parameter. So that the system can work
optimally..
Startup setting: uplink and downlink gain setting. To see the detail in the section 4.2.2
Power Amplifier and Low Noise Amplifier Gain Setting.
See test flowing chart on Figure 16: