Brannstrom Sweden AB
CleanTrack 1000B - Rev 2.20xd, 2019
Page
23
of
232
4.7. First Start up Checklist
Very important that all electrical wires are properly tightened. A wire that falls on secondary side of the zener barriers
or on an explosion proof electrical sample pump connection might cause serious damage.
Reference should also be made to chapter
page
page
1.
Check that the supply voltage, to be connected to the Converting Unit (Cb1) corresponds to the voltage mark,
normally placed on lower left side inside the unit.
2.
Check that all Zener Barriers are connected correctly (Cb7, Cb3 and optionally Cb3a). Verify that the
intrinsically safe arrangements are in order for the cables. See chapter
4.11. Calculations on intrinsically safe
page
3.
Check the Sample Pump connection (Cb2 or Cb4), communication to Computer Unit (Cb5) and eventual other
connections to the Converting Unit PCB.
If an explosion proof electrical sample pump is used:
o
check the motor frame to be connected to earth and that a correct cable gland is used and tightened.
If an electrical motor bulkhead sample pump is used:
o
check and/or refill oil in pump shaft seal. See chapter
9.7. Sample Pump Shaft seal oil refilling
page
If an air motor sample pump is used:
o
it is important that eventual residues from work with the air pipe and other activities are removed
from the piping before the pipe is connected to the analyzing unit or the Speck air sample pump.
These residues might harm the motor of the Speck air sample pump.
o
drain the water trap and adjust the pressure regulator until the pressure gauge in the Analyzing Unit
cabinet shows 5.2 bar. See drawing:
CTB10010 sheet 5 of 5, Analyzing unit with air motor sample
page
item d6.
4.
If an electric sample pump is used, check the setting of the overcurrent relay to correspond to the current of the
electrical sample pump motor. See item d1 of drawing:
CTB10003 sheet 3 of 4, Converting Unit
page
5.
Connect mains to the converting unit and check that at least one light emitting diode on top right of both
PCB’s in the unit are lit or flashing.
6.
Check that the supply voltage to be connected to the Computer Unit (Cb8b) corresponds to the voltage mark,
normally placed on the lower left side inside the unit.
7.
On the Computer unit also check connections for valve(s) (Cb8a) and feedback(s) (Cb13), for communication
to Converting Unit (Cb5), GPS input (Cb29) and Log input (Cb12) if speed log is used.
8.
Connect mains to the computer unit. After a few seconds 2 different “Brannstrom Sweden” will appear on the
screen before the screen goes black again and about 2 minutes later the Cleantrack1000B software appears.
9.
The following should be set up or checked at the Computer Unit, refer to chapter
page
•
Sample pump selected.
•
Flushing water configuration.
•
Manual override settings.
•
Converting unit type setting.
•
Valve control and feedback.
•
Pressure transmitter programming and limits.
•
Flow meter programming and limits.
•
Speed log programming and limits.
•
GPS input.
•
Printer option.
for alarms and consult chapter
page
for fault finding.
Communication is continuously going on between the Computer Unit, the Converting Unit and the Measuring Cell.
This gives that all communications must be in working order, if not communication alarms are generated.
If an air motor sample pump is used a second adjustment of the pressure regulator should be made while the sample
pump is running. Setting the pressure gauge in the Analyzing Unit cabinet to 5.2 bar while the sample pump is running
will also compensate for the pressure drop in the air pipe to the Analyzing Unit.
It should be checked that a running sample pump stops and activate a
"40 Alarm - High Work Pressure"
if a valve on
the sample outlet line is closed.
It should be checked that a running sample pump stops and activate a
"41 Alarm - Low Work Pressure"
if a valve on
the sample inlet line is closed.
To make suitable settings, see chapter
page
page
The pressure alarms above are important to avoid to harm the Sample Pump unit, by pumping towards a closed valve
(blockage) or pumping when dry (starvation). The pressure alarms are also important to detect a “loss of sample”.
After finishing the first start-up it is recommended to save settings on a USB-stick. See chapter
page
Содержание CleanTrack 1000 B
Страница 26: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 26 of 232 ...
Страница 27: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 27 of 232 ...
Страница 28: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 28 of 232 ...
Страница 29: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 29 of 232 ...
Страница 31: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 31 of 232 ...
Страница 32: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 32 of 232 ...
Страница 101: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 101 of 232 Drawing CTB10003 sheet 2 of 4 Converting Unit ...
Страница 102: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 102 of 232 Drawing CTB10003 sheet 3 of 4 Converting Unit ...
Страница 103: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 103 of 232 Drawing CTB10003 sheet 4 of 4 Converting Unit ...
Страница 113: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 113 of 232 ...
Страница 119: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 119 of 232 10 4 SPP 100 Sample pump with Ex Motor ...
Страница 120: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 120 of 232 ...
Страница 122: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 122 of 232 ...
Страница 123: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 123 of 232 ...
Страница 125: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 125 of 232 Drawing CT900907 1 Matre Bulkhead Sample pump ...
Страница 127: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 127 of 232 Drawing CTB10021 sheet 2 of 2 Connection box ...
Страница 148: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 148 of 232 11 Approval Certificates 11 1 Certificate MED D ...
Страница 149: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 149 of 232 ...
Страница 150: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 150 of 232 11 2 Type Approval DNV ...
Страница 151: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 151 of 232 ...
Страница 152: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 152 of 232 ...
Страница 153: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 153 of 232 ...
Страница 154: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 154 of 232 11 3 Type Approval Germany ...
Страница 155: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 155 of 232 ...
Страница 156: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 156 of 232 ...
Страница 157: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 157 of 232 ...
Страница 158: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 158 of 232 11 4 IMO Certificate CCS ...
Страница 159: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 159 of 232 ...
Страница 160: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 160 of 232 11 5 Type Approval CCS ...
Страница 161: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 161 of 232 ...
Страница 162: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 162 of 232 ...
Страница 163: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 163 of 232 11 6 Type Approval NK ...
Страница 164: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 164 of 232 11 7 Type Approval RMRS ...
Страница 165: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 165 of 232 ...
Страница 167: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 167 of 232 ...
Страница 168: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 168 of 232 ...
Страница 169: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 169 of 232 12 2 ATEX Certificate Zener Barrier PCB ...
Страница 170: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 170 of 232 ...
Страница 171: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 171 of 232 ...
Страница 172: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 172 of 232 ...
Страница 173: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 173 of 232 ...
Страница 174: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 174 of 232 12 3 ATEX Certificate Measuring Cell ...
Страница 175: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 175 of 232 ...
Страница 176: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 176 of 232 ...
Страница 177: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 177 of 232 ...
Страница 178: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 178 of 232 12 4 Pressure transmitter Danfoss ...
Страница 179: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 179 of 232 ...
Страница 180: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 180 of 232 ...
Страница 181: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 181 of 232 ...
Страница 182: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 182 of 232 ...
Страница 183: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 183 of 232 ...
Страница 184: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 184 of 232 ...
Страница 186: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 186 of 232 ...
Страница 187: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 187 of 232 12 5 2 ATEX Certificate ...
Страница 188: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 188 of 232 ...
Страница 189: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 189 of 232 ...
Страница 190: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 190 of 232 12 6 Flow meter Siemens ...
Страница 191: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 191 of 232 ...
Страница 192: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 192 of 232 ...
Страница 193: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 193 of 232 ...
Страница 194: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 194 of 232 ...
Страница 195: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 195 of 232 ...
Страница 196: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 196 of 232 ...
Страница 197: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 197 of 232 ...
Страница 198: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 198 of 232 12 7 Flow meter Fuji ...
Страница 199: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 199 of 232 ...
Страница 200: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 200 of 232 ...
Страница 202: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 202 of 232 ...
Страница 203: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 203 of 232 ...
Страница 204: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 204 of 232 ...
Страница 205: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 205 of 232 12 8 2 Elprom Certificate EPT 17 ATEX 2588 X ...
Страница 206: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 206 of 232 ...
Страница 207: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 207 of 232 ...
Страница 208: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 208 of 232 ...
Страница 209: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 209 of 232 12 8 3 Elprom Certificate EUM1 10 ATEX 0350 ...
Страница 210: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 210 of 232 ...
Страница 211: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 211 of 232 ...
Страница 212: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 212 of 232 ...
Страница 213: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 213 of 232 ...
Страница 214: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 214 of 232 ...
Страница 215: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 215 of 232 ...
Страница 216: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 216 of 232 ...
Страница 217: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 217 of 232 ...
Страница 218: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 218 of 232 ...
Страница 219: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 219 of 232 ...
Страница 220: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 220 of 232 ...
Страница 221: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 221 of 232 ...
Страница 222: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 222 of 232 ...
Страница 223: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 223 of 232 ...
Страница 224: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 224 of 232 ...
Страница 225: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 225 of 232 ...
Страница 227: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 227 of 232 ...
Страница 230: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 230 of 232 This page is intentionally left blank ...
Страница 231: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 231 of 232 14 Project specific drawings and data sheets ...
Страница 232: ...Brannstrom Sweden AB CleanTrack 1000B Rev 2 20xd 2019 Page 232 of 232 This page is intentionally left blank ...