22/28 Commissioning
Bosch Rexroth AG
, VT-SVTSY-1-1; RE 29681-B/11.2019
For the external supply voltage of the test device, functional low voltages with
electrical separation (PELV or SELV) according to VDE0100, part 410 must be
applied.
For the external voltage supply, it must be ensured that, even in the event of a
fault, the voltage limits defined for the test device are not exceeded. PELV power
supply units according to EN 60204, section 6.4.2 comply with these requirements.
▶
For signal cables, use only cables with a copper braid shield.
▶
Do not route signal cables through strong magnetic fields.
▶
Lay signal lines as continuously as possible.
8 Commissioning
WARNING
Improper commissioning!
Risk of damage to property and personal injuries. Commissioning of the
test device requires basic knowledge in the field of hydraulics and electrics/
electronics.
▶
The test device may only be commissioned by qualified staff.
8.1 Initial commissioning
▶
Only commission a completely connected product.
▶
Allow the test device to acclimatize for some time prior to commissioning as the
electronics might be damaged by the formation of condensed water.
9 Operation
CAUTION
Mutual influencing of devices!
Unforeseeable movements of the system!
▶
Make sure that neither the test device can be influenced by other devices nor
other devices can be influenced by the test device.
Only specialist personnel who have electrical and hydraulic knowledge may
operate the device in a controlled electromagnetic environment.
Power supply
Shielding
General notes on wiring