STEP #1
INSTALLING THE EMERGENCY BALLAST
> Mount the emergency ballast and battery inside the fixture.
STEP #2
INSTALLING THE TEST SWITCH
> Install the test switch on the fixture so it can be accessed after
fixture installation.
> See illustration below showing basic switched and unswitched
fixture connections for test switch installation. Refer to the
diagrams and wire the test switch so that it removes AC power
from both the emergency ballast and the AC ballast at the same time.
> Drill a 1/2" hole and install the switch as shown.
STEP #3
STEP 1
STEP 2
NOTE: After installing the charging indicator light and test switch, mark each with the appropriate label.
> Install the CHARGING INDICATOR LIGHT
as shown in the illustration so it will be
visible after the fixture is installed.
INSTALLING THE CHARGING INDICATOR LIGHT
NOTE:
Make sure that the necessary branch circuit wiring is available. An unswitched
source of power is required. The emergency ballast must be fed from the same
branch circuit as the AC ballast.
WARNINGS:
1. TO PREVENT DAMAGE TO THE EMERGENCY BALLAST, JOIN THE BATTERY CONNEC-
TOR BEFORE SUPPLYING AC POWER TO THE EMERGENCY BALLAST.
2. TO PREVENT HIGH VOLTAGE FROM BEING PRESENT ON RED & YELLOW OUTPUT
LEADS PRIOR TO INSTALLATION, INVERTER CONNECTOR MUST BE OPEN. DO NOT JOIN
INVERTER CONNECTOR UNTIL INSTALLATION IS COMPLETE AND AC POWER IS
SUPPLIED TO THE EMERGENCY BALLAST.
Fixture
Test Button
Hex Nut
Hex Nut
Test Switch
Leads
Push to Test
INSTALLATION
Charging
Indicator
Light
1/2" White
Bushing
Violet (+)
Brown (–)
Violet (+)
Brown (–)
1/2" White
Bushing
5/8" Black
Bushing
5/8" Black
Bushing
1/2" Punch
Fixture
Fixture
Charging
Indicator
Light
2