3. MOUNTING INSTALLATION 

3.1 

CEILING MOUNTING 

 

IMPORTANT!

 Ensure that the ceiling is capable of taking the weight of the heater. 

For  optimum  results  do  not fit  in ceilings  higher  than  3m.  Air  is  taken  in  through the large  grille  and discharged  through the  smaller  grille.  The  air 
intake  and  discharge  areas  must  be  kept  completely  clear  for  a  minimum  of  1.5m  from  the  front  of  the  heater.  In  an  area  using  multiple  units, 
heaters should be spread to provide an even heat distribution. 
Remove the front grille / cover by undoing the 8 screws securing it in place (You d

on’t need to remove this cover if using M6 drop rods or M6 hanging hooks.) 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Using the drawing above mark out the holes required to secure the heater case to the ceiling. Use the 4 x keyhole slots and an additional 2 holes (at 
least one each side) once installed to lock the heater in place. 

These additional 2 holes MUST be used to stop the possibility of the case sliding off its Keyhole fixings. 

Secure to the ceiling using suitable fixings (not supplied). It will be easier to do some of the electrical connections before finally securing to the ceiling. 

3.2  DROP ROD MOUNTING 

The heater has 4 x M6 threaded holes and 4 x M10 keyhole holes suitable for using M6 or M10 drop rod studding. If using M6 threaded holes fully 
screw the studding into each hole and use a lock nut to stop it rotating and coming out. If using M10 studding a nut must be placed and tightened 
above and below the case on each of the 4 studs to hold the case securely to the M10 drop rods (Removal of the grille / guard will be needed so 
you can add an M10 Nut inside the heater). Use the diagram above to determine the spacing of the drop rods. If you use drop rods you should be 
able to gain access to all the electrical connections after you mount the heater. 

 

 

4.  ELECTRICAL CONNECTIONS 

4.1  230V SINGLE PHASE 

– Without controls. 

Please make sure you have read the Safety instructions and that you are a suitably qualified electrician before continuing. 
Drawings show connections inside the black terminal box on the outside of the heater. 

Do NOT use power tools to undo or do up terminal screws.

 

Please Note:- Specified cable sizes are for typical installations, correction factors may need to be used when determining actual cable sizes. 

 

Standard Connection and Use 
 
Use 1.5mm² 3 Core Mains Cable (see note above). 
Connect Brown wire 

– Terminal 1 or L. 

Connect Blue wire 

– Terminal 5 or N. 

Connect Green / Yellow wire 

– Terminal E or 

 
Ensure the 3 links 

are  in  position  between  terminals  1 

and 2, 2 and 3, 3 and 4 as shown in drawing to the left. 
 
If you wish to de-rate the heater from 3kW to 2kW remove the link 
between  terminal  3  and  terminal  4.  Ensure  you  tighten  up  the 
screws after removing the link. See drawing to the right. 
 

PLEASE CHECK ALL CONNECTIONS BEFORE TURNING ON 

AS INCORRECT WIRING IS NOT COVERED BY THE 

GUARANTEE 

 

Control Box 