Adding battery modules
3.
Check the voltage of the new modules. The
voltage should be between 46 V and 56 V.
4.
Adjust the voltage of the battery system to ±1 V
to the voltage of the new modules (see Appendix
8.3). An exactly adjusted module voltage avoids
adjustment in the system and allows immediate
access to the full capacity.
5.
Disconnect the inverter from voltage and switch off Hyperion.
6.
Install the new modules. See chapter 3.3 Assembly.
7.
Put the system into operation. See chapter 3.4.
3.3.5
Disposal
Dispose of transport packaging for recycling in accordance with the statutory
provisions.
It is recommended to keep not required parts (patch cables, dummy plugs, screws)
together with the installation instructions near the battery system.
Before removing defective modular batteries, the power socket must be taped with
insulating tape after removing the power plug.
3.4
Connecting the inverter
3.4.1
SMA Sunny Boy Storage 3.7 / 5.0 / 6.0
1.
Feed the DC power cable, PE as well as the communication cable(s)
through the respective PG screw glands into the connection
compartment of the inverter.
2.
Connect the cables in the inverter according to the Sunny Boy Storage
3.7 / 5.0 / 6.0 operating instructions.
Instructions
Figure 7:
Connecting the
SMA SB Storage to the
BMZ Hyperion
Содержание Hyperion 15
Страница 1: ...ORIGINAL INSTALLATION INSTRUCTIONS Hyperion Lithium Ion Energy Storage ...
Страница 27: ......