MPEG4 HD IP Encoder User Manual
Chapter 2 Installation Guide
This section is to explain the cautions the users must know in some case that possible
injure may bring to users when it’s used or installed. For this reason, please read all details
here and make in mind before installing or using the product.
2.1 General Precautions
•
Must be operated and maintained free of dust or dirty.
•
The cover should be securely fastened, do not open the top case of the products
when the power is on.
•
After use, securely stow away all loose cables, external antenna, and others.
2.2 Power precautions
•
When you connect the power source, make sure to not overload it.
•
Avoid operating on an open wet floor. Make sure the extension cable is in good
condition
•
Make sure the power switch is off before you start to install the device
2.3 Device’s Installation Flow Chart Illustrated as following
Connecting
Grouding
Wire and
Power
Cord
Acquisition
Check
Installing
Device
Setting
Parameter
Running
Device
Connecting
Signal
cable
2.4 Environmental Requirements
Item
Requirement
Machine Hall
Space
When user installs machine frame array in one machine hall, the distance between 2 rows
of machine frames should be 1.2~1.5m and the distance against wall should be no less
than 0.8m.
Machine Hall
Floor
Electric Isolation, Dust Free
Volume resistivity of ground anti-static material: 1X107~1X1010
Ω
,
Grounding current
limiting resistance: 1M
Ω
(Floor bearing should be greater than 450Kg/
㎡
)
Environment
Temperature
5~40°C (sustainable )
,
0~45°C (short time)
,
installing air-conditioning is recommended
Relative
20%~80% sustainable 10%~90% short time