A. INSTALLATION GUIDE 4.       INSTALLATION OF THE TANKS 

 

 

PAGE

 14 / 51

Installation and User guide – ECOROCK - Systems – 26-05-2016 

 

4.2.2  Installation of the tanks in dry ground conditions 

 

 

Once the base of the excavation is stable, the installation can begin 

 

The Primary Tank should not be positioned horizontally; it must have a slight gradient  

 

towards the water outlet 

 

Before connecting any water or ventilation pipes, ensure that the units are perfectly  

 

installed 

 

Ensure that all levels are correct so that the wastewater can flow freely through the system 

 

Check that all connections are correctly positioned 

 

Ensure that the seals are watertight 

 
 

4.2.3   Backfilling in dry ground conditions 

 

 

Backfill the hole with 3 to 6 mm smooth pea gravel, or lean-mix concrete whilst filling the  

 

tanks with water at the same level 

 

Do not exceed 300 mm per filling and compaction cycle 

 

Make sure that the BIOROCK® media is completely saturated with water 

 

Do not backfill with the soil removed during the excavation: roots and stones can damage  

 

the tank.  

 

Do not compact the backfill material mechanically: compact manually. 

 

Backfilling around and filling both the Primary Tank and BIOROCK® unit with water should  

 

take place at the same time. 

 

Once the backfilling is finished and compacted, check the levels of the tanks again 

 

The lids or access covers of the system should be installed just above ground, level to  

 

provide easy access for maintenance.  

 

Close and secure all covers with screws  

 

Complete the backfilling once all pipework has been checked and connected.  

 
 

4.3   INSTALLATION IN HIGH GROUND WATER CONDITIONS 

Appendix «Installation in high ground water conditions» 

 

The ECOROCK units can be installed in high ground water conditions with special precautions. 
If you don’t use a BIOROCK® Primary Tank, please confirm with the other manufacturer that 
this Primary tank is suitable for high ground water conditions. 

 
 

 

If you don’t use a BIOROCK® Primary Tank, please consult the manufacturer to 
ensure this Primary Tank is suitable for high ground water conditions. 

 

 

The level of the water table must never exceed the level of liquid inside the Primary 
Tank. Extremely high water tables signify a flood risk which could cause water ingress 
or collapsed tanks. 

 
 

Содержание ECOROCK-1500

Страница 1: ...PAGE 1 51 Installation and User guide ECOROCK Systems 26 05 2016 INSTALLATION USER GUIDE FOR THE BIOROCK SYSTEMS ECOROCK 1500 ECOROCK 2000 ECOROCK 3000...

Страница 2: ...PAGE 2 51 Installation and User guide ECOROCK Systems 26 05 2016 TABLE OF CONTENTS A INSTALLATION GUIDE 5 B USER GUIDE 23 C APPENDICES 34...

Страница 3: ...IOROCK distributor for any queries or further assistance Thank you for choosing BIOROCK The installation and commissioning of your BIOROCK system should be carried out by a BIOROCK trained and approve...

Страница 4: ...A INSTALLATION GUIDE PAGE 4 51 Installation and User guide ECOROCK Systems 26 05 2016 A INSTALLATION GUIDE ECOROCK SYSTEMS...

Страница 5: ...tion of the Primary Tank 12 4 1 3 Installation of the BIOROCK treatment unit 12 4 2 Installation in dry ground conditions 13 4 2 1 Installation and digging in dry ground conditions 13 4 2 2 Installati...

Страница 6: ...nly domestic sewage should enter the system no rainwater is allowed To ensure the good working order of the BIOROCK system the use of automatic toilet cleaners electric waste disposal systems and pump...

Страница 7: ...of the tank enable a safe movement by fork lift Four lifting eyes are situated on the top corners of each tank enabling lifting by crane or JCB The tanks should be handled transported and stored with...

Страница 8: ...ell problems but also to evacuate the produced gasses A Primary Tank generates malodorous gases like sulfur hydrogen H2S An evacuation of the gasses is necessary to avoid that H2S will be transformed...

Страница 9: ...it must flow by gravity to the next stage or a discharge point 2 3 ECOROCK TREATMENT UNIT TECHNICAL The tanks and covers are made of polyethylene Each tank has two lifting eyes that are situated at th...

Страница 10: ...t should be installed When using a final effluent pump the pump shaft can be used as a sampling shaft 3 1 INSTALLATION LAYOUT N 1 GRAVITY DISCHARGE non electric 3 2 INSTALLATION LAYOUT N 2 PUMPED DISC...

Страница 11: ...tanks with water before unit is backfilled DO NOT use dirty or contaminated water DO NOT use a mechanical compactor only compact manually DO NOT reuse the excavated soil or spoil from the site DO NOT...

Страница 12: ...he primary tank and the treatment unit is 300 mm The distance between the side of the excavation and the tanks must be minimum of 300 mm Connections for the BIOROCK system are made with flexible seals...

Страница 13: ...mp The seals on the BIOROCK tanks are flexible and have a diameter of 110 mm The discharge pipe for the treated effluent should have a minimum gradient of 1 4 1 3 Installation of the BIOROCK treatment...

Страница 14: ...damage the tank Do not compact the backfill material mechanically compact manually Backfilling around and filling both the Primary Tank and BIOROCK unit with water should take place at the same time O...

Страница 15: ...the base of the tanks on all sides If you are unsure a qualified civil engineer should be consulted Anchoring the tanks to the base is achieved with a system using the anchoring points these are posit...

Страница 16: ...ipes ensure the units are perfectly installed and stable on the excavation base Ensuring that all levels are correct is crucial if the wastewater is to flow efficiently through the system Pay special...

Страница 17: ...tions the thickness of the slab distribution the access to the lids of the tanks the unit and sampling pipe the reinforcement and the structure of the slab etc will be specified by a qualified civil e...

Страница 18: ...e that the ventilation works properly Always check the efficiency of the ventilation in both the primary tank and the treatment units with a smoke test If the site is not suitable for non electric ven...

Страница 19: ...heck the ventilation with a smoke test in representative conditions calm weather and storms are not representative conditions If the ventilation is not working properly Check the ventilation system ag...

Страница 20: ...edia may be rinsed if blocked or contaminated with solids In this case we recommend taking out the upper bags rinsing them if possible and placing them back For your safety always contact BIOROCK or y...

Страница 21: ...d clean it before the restart If a pump station is installed it is best to commission it and clean it before the shutdown period The BIOROCK system remains efficient after a shutdown period 7 CONFORMI...

Страница 22: ...truction defect acknowledged by the supplier the warranty is limited to the replacement of defective parts excluding all other costs involved The defective equipment and accessories will be repackaged...

Страница 23: ...B USER GUIDE PAGE 23 51 Installation and User guide ECOROCK Systems 26 05 2016 B USER GUIDE FOR THE BIOROCK SYSTEMS ECOROCK 1500 ECOROCK 2000 ECOROCK 3000...

Страница 24: ...IONS 25 2 SUSTAINABLE DEVELOPMENT 26 2 1 Useful information 26 2 1 1 Sustainability 26 2 1 2 Waste disposal 26 2 2 Polyethylene and PVC 27 2 2 1 Energy recovery 27 2 2 2 Material recycling 27 2 2 3 Th...

Страница 25: ...t the clean water from the System is NOT drinkable NOTE Always keep the lid closed and open it only for inspections and maintenance work Never leave the lids and inspection points unsupervised while o...

Страница 26: ...2 1 USEFUL INFORMATION 2 1 1 Sustainability Sustainable development is based on three factors Protection of the environment social progress and economic development Both production methods and consump...

Страница 27: ...cs of this nature PVC PE into granules or powder which can be sold as an alternative to virgin material in manufacturing 2 2 3 The BIOROCK media The BIOROCK media is inert but if there is a need to re...

Страница 28: ...ear Visually check the water tightness of the complete system Check the ventilation Check if there are any smells exiting the tanks PRIMARY TANK Every year Check the sludge level Empty the Primary Tan...

Страница 29: ...sed deposits in the pre treated waste water this may be caused by Water flowing too fast through the PT too short retention time hydraulic overload Check that no rainwater run off system passes throug...

Страница 30: ...be retained by the owner in and placed in the maintenance guide The septic tank emptier should pressure wash the sides of the tank and the Effluent Filter to remove the accumulated fats and other mat...

Страница 31: ...bottom of the sampling glass after it has rested for twenty minutes The water shouldn t have a septic or nauseating odor It may have the characteristic smell of fresh humus If the visual check seems...

Страница 32: ...rings are put back to the same position and height Above the aeration rings the BIOROCK media with the dimension of 10x10x10 mm is laid A well performing BIOROCK unit does not produce a bad smell it...

Страница 33: ...ffluent or an accumulation of suspended solids at the top layer of BIOROCK media then the BIOROCK media may need to be cleaned more thoroughly For this please contact your supplier or maintenance serv...

Страница 34: ...ater distribution schematic of an ECOROCK 3000 44 1 11 Cross section of the layers of BIOROCK Media in an ECOROCK 3000 unit 45 Appendix 2 Installation drawings of the ECOROCK installations 2 1 Drawing...

Страница 35: ...C APPENDICES PAGE 35 51 Installation and User guide ECOROCK Systems 26 05 2016 Drawing of an ECOROCK 1500 treatment unit APPENDIX 1 1 1...

Страница 36: ...C APPENDICES PAGE 36 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 2 Aeration and water distribution scheme without pumping well...

Страница 37: ...C APPENDICES PAGE 37 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 3 Drawing Cross section showing the layers of BIOROCK Media in a ECOROCK 1500 unit...

Страница 38: ...C APPENDICES PAGE 38 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 4 Drawing of an ECOROCK 1500 treatment unit...

Страница 39: ...C APPENDICES PAGE 39 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 5 Aeration and water distribution scheme without pumping well...

Страница 40: ...C APPENDICES PAGE 40 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 6 Drawing of an ECOROCK 2000 treatment unit...

Страница 41: ...C APPENDICES PAGE 41 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 7 Aeration and water distribution scheme without pumping well...

Страница 42: ...C APPENDICES PAGE 42 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 8 Drawing Cross section showing the layers of BIOROCK Media in a ECOROCK 2000 unit...

Страница 43: ...C APPENDICES PAGE 43 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 9 Drawing of an ECOROCK 3000 treatment unit...

Страница 44: ...C APPENDICES PAGE 44 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 10 Aeration and water distribution scheme without pumping well...

Страница 45: ...C APPENDICES PAGE 45 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 1 11 Drawing Cross section showing the layers of BIOROCK Media in a ECOROCK 3000 unit...

Страница 46: ...C APPENDICES PAGE 46 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 1 2 1 APPENDIX 2 2 2...

Страница 47: ...C APPENDICES PAGE 47 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 2 2 3 APPENDIX 2 2 4...

Страница 48: ...C APPENDICES PAGE 48 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 2 2 5 APPENDIX 2 2 6...

Страница 49: ...C APPENDICES PAGE 49 51 Installation and User guide ECOROCK Systems 26 05 2016 APPENDIX 2 2 7 APPENDIX 2 2 8...

Страница 50: ...COMMISSIONING Product N of tank see page 9 in the user s guide Warning Please keep sludge emptying documents and proofs validated by the contractor DATE WHAT HAS BEEN DONE USER S NAME COMMENTS If you...

Страница 51: ...C APPENDICES PAGE 51 51 Installation and User guide ECOROCK Systems 26 05 2016...

Отзывы: