ASSEMBLY,  INSTALLATION  AND  COMMISSIONING 

Positioning the PVB distributor: 

o

 

When installing the distributors it must be ensured that they are positioned as close as possible and in the centre  
of the connected lubrication points (as far as possible). 
 
 
 
 

o

 

The PVB distributors must be easily accessible for maintenance and monitoring purposes. 

 
Fitting the pipelines or hoses: 

 

WARNING 

 

o

 

The lubrication lines must be filled with lubricant before fitting. 

o

 

Only clean grease or oil may be used!  
Particles of dirt can block the distributor and cause the system to fail! 

o

 

Cleanliness must be maintained during installation!  

o

 

The pipelines must be checked for any contamination (e.g. shavings, etc.)and cleaned if necessary before being  
filled with lubricant and connected to the distributor. 

 
 Commissioning: 

 
 

o

 

Ensure that the distributor and all the connected pipes are correctly installed before you operate the distributor and 
lubrication system. 

o

 

Ensure that the pump that is connected cannot exceed the permitted operating pressure for the distributor or that it is 
equipped with a pressure relief valve. Especial care should be taken when using manual lube guns. Most of these can 
easily produce a pressure of over 500 bar. 

o

 

Monitoring the system pressure with a manometer or pressure switch is recommended. 

o

 

Once fitted, check the proper operation and impermeability of the system at each installed distributor and lubrication 
point. 

 
Example of installation: 
 
 
 
 
 
 
 

 
 
 
 
 
 

Continuous operation:

 

 

The distributor is designed for continuous operation. Care should be taken during the entire operating phase that the 
specified operating pressure and temperature range are not exceeded.  Only approved lubricant which is free of 
contamination may be used.  
 
Disassembly: 
 
 
The distributor must only be disassembled when it is at a standstill and depressurized.

 

 

 

 

Содержание PVB series

Страница 1: ...1 BIJUR DELIMON INTERNATIONAL BA_2017_1_GB_PVB Operating manual Progressive Block Distributor PVB BA_2017_1_GB_PVB...

Страница 2: ...ion for competition purposes Company address spare parts and service address DELIMON GmbH Arminstra e 15 D 40277 D sseldorf Phone 49 211 7774 0 Fax 49 211 7774 210 Branch office Am Bockwald 4 D 08344...

Страница 3: ...has to take care that all the maintenance inspection and installation work is executed by authorized and qualified skilled personnel who have informed themselves adequately by thoroughly studying the...

Страница 4: ...ND FUNCTION PVB distributors are piston distributors which evenly distribute the supplied lubricant This is achieved by means of metal sealing pistons which dispense the lubricant to the connected lub...

Страница 5: ...outlets or outlets that are opposite each other in order to achieve a higher metered volume for individual outlets for example WARNING Special fittings with non return valves similar to DIN 2353 CLL...

Страница 6: ...modification of the outlets is listed in Chapter 9 Accessories Monitoring The PVB distributor can be fitted with a motion indicator on the last outlet pair for visually monitoring the piston movement...

Страница 7: ...valves Suitable lubricants based on mineral oil Grease NLGI class 000 to 2 DIN 51818 Oil ISO VG 68 to 1500 operating viscosity DIN 51519 Synthetic lubricants on request The NLGI class as per DIN 5181...

Страница 8: ...reversal yes Supply line short circuit protection no Circuit diagram and dimensions Electrical monitoring 76925N018 pressure resistant version 350 bar Type of protection IP 67 Operating voltage 10 to...

Страница 9: ...ght connection open E right outlet open left closed CA c left connection open F both outlets closed CC c connections open on both sides G both outlets closed BC b connection and c right connection ope...

Страница 10: ...factor is only the pumping capacity and its distribution over the PVB distributor as the following example shows Pumping capacity 12 cm3 min Distributor configuration 1 3 x 0 4 cm3 Distributor config...

Страница 11: ...lubrication quantity over several intervals e g 2x per hour Further details on the mode of operation and control of progressive systems can be found in the general description of the system We are ha...

Страница 12: ...ding 03 has to order separately if stainless steel of plug in fittings is required The number of fittings depends on the number of outlet selection not suitable for 350 bar version Assembly anf fittin...

Страница 13: ...e used to assemble the pipelines and cutting ring fittings Please contact our service department if necessary We can provide service engineers or supervisors for assembly training and induction either...

Страница 14: ...oning o Ensure that the distributor and all the connected pipes are correctly installed before you operate the distributor and lubrication system o Ensure that the pump that is connected cannot exceed...

Страница 15: ...ting procedure 1 Make sure that the pump is supplying lubricant Remove the inlet fitting on the PVB distributor and let the pump run until lubricant comes out of the open line If there is no supply of...

Страница 16: ...type Application FZ A or FZ B Pump three phase motor 8 15 30 litre container up to 200 bar up to 12 outlets robust design for harsh industrial environment for specific requirements for motors power s...

Отзывы: