background image

 

free of contaminants.  This will prevent tracking on the outside 
of the probe and meter error. 

3.

 

Always confirm internal battery voltage before and after use. 

DESIGN and FUNCTION

 

 

The  HI  POT  meter  is  designed  to  HI  POT  cable  at  7.2kV  phase  to 
ground. The hi-pot DC diode is built into the meter and the  interconnect 
cable between the meter and second probe is removable and available in 
varying lengths. 
There are two selector toggle switches on meter, one on the back and one 
on the side of the meter housing.  The toggle on the back allows the user 
to select between 7.2kV Test.  The selector switch located on the side 
allows the user to test the meter operation and turn on an LED back light 
for low light work conditions. 
 
Note: Meter back-light and test operate off of a 9volt battery located in 
the meter housing.  The meter will still operate with a dead battery but 
the light and test functions will not. 
 

BATTERY REPLACEMENT

 

 

The threaded live line tool fitting on the face of the meter probe is 
furnished with two flat edges for use with a wrench or slip joint pliers to 
remove and install the fitting from the meter housing. To remove, turn 
the live line tool fitting in a counterclockwise direction and install in a 
clockwise direction.   

 

METER SET-UP and TESTING 
 

WARNING

 

 

see “Product Safety Information”, page 3.

 

 

see “Inspection & Maintenance”, page 3.

 

 

1.

 

Attach the interconnect cable to the meter probe and second 
probe. 

2.

 

Test the meter by flipping the toggle on the back of the meter 
housing to the test position. Then move the small side switch to 
the momentary on position to activate the test. The needle should 
move smoothly all the way to the far right, at or past the red 
indication area. 

Отзывы: