COMMISSIONING
7
COMMISSIONING
7.1 Warnings
The commissioning of this boiler and sys-
tem must only be undertaken by a profes-
sionally qualified person in accordance
with the requirements of the Gas Safe In-
stallation and Use Regulations and be ap-
proved by Gas Safe.
Ensure that the Benchmark Checklist is
satisfactorily completed during the com-
missioning process. The Checklist is
located at the end of this manual. This
manual should be handed to the User fol-
lowing completion of the installation and
commissioning process. Failure to comply
with these requirements may invalidate the
manufacturers guarantee.
For Ireland (IE), it is necessary to complete
a “Declaration of Conformity” to indicate
compliance to I.S.813.2002.
7.2 Electrical installation
Preliminary electrical system checks to en
-
sure electrical safety shall be carried out by a
competent person. i.e. polarity, earth continu
-
ity, resistance to earth and short circuit.
If a fault has occurred on the appliance the
fault finding procedure should be followed as
specified in the service manual.
7.3 Gas supply installation
•
Inspect the entire installation including the
gas meter, test for tightness and purge, all
as described in BS 6891;
For Ireland (IE), refer to I.S.813.2002.
•
Open the gas cock 12 (Fig. 7.1) on the ap
-
pliance and check the gas connector on the
appliance for leaks.
Fig. 7.1
12
Open
position
7.4
Initial filling of the system
•
Open the c.h. flow and return valves.
•
Remove the front panel of the case (
section
"Dismantling the external panels" to page
50).
•
Unscrew the cap on the automatic air purger
valve 23 in
Fig. 7.2
one full turn and leave
open permanently.
Fig. 7.2
23
•
Gradually open stopcock at the filling point
connection to the c.h. system until water is
heard to flow; do not open fully.
•
Open each radiator air vent starting at the
lowest point of the system and close it only
when clear water, free of bubbles, flows out.