LPR Meter
Handbook
Page 3
3. Operating
Instructions
Set Up
The following section provides a step by step guide to the
operating instructions for the corrosion rate meter.
The above diagram provides the connections required to
carry out the corrosion rate measurement. Note that either
two connections are provided to the reinforcement or a
single connection is acceptable if less than 10metres. In this
application a link is required to interconnect the WE and SE
terminals on the meter.
Reinforcement
Reference Electrode
Auxiliary
Electrode
Big Foot