7.
Install (2) two 4-1/4" siding panels over
the door header. The siding should extend
3/4" below the door header. Cut length to
fit. Wall trim, installed later, will hide
where the siding butts the front wall siding.
Step 7
Set Walls
2.
Erect wall panels. IMPORTANT make sure walls are plumb and square. Secure together
at the corners using (4) four 10d sinkers per corner.
3.
Nail along siding edge where it overlaps front and back walls at corners.
4.
Install the 2x4 door header between the front wall panels. Nail through the wall stud into the
ends of the header. Toenail into the top wall plates.
5.
Remove the center (2) two 2x4-84" boards from pallet and temporarily install at both sides of
the door opening to hold the wall straight. Alternatively you can use 2x4-72" boards that will
be used later for tie plates.
6.
Nail all wall panels to the floor through the bottom plate. Space 10d sinkers 24" apart.
2x4 Door Header
Drawing shows a building
with the doors offset.
OSB Filler
1.
Gather (2) two 67-1/2" long 2x4 boards and a
3-1/4" x 67-1/4" OSB filler panel. Glue both
sides of OSB. Nail header together from both
sides with 10d sinkers staggered 6" apart.
67-1/2" Long 2x4
Nail siding
Cut 4-1/4" x 48" Siding
Panels to Fit
3/4" Below
Bottom of Header