CHECKS

 

 
To ensure that the heater is working correctly certain 
criteria need to be checked. Start up heater and check 
 the following 

 

35

4

200

1

2

100

1

 

  Check that the fan starts approximately 30 seconds 

after ignition of the burner. 

 
When the heater is at its full efficiency after about 20 
minutes the following checks should be made 
 
Check that the horizontal fins are correctly set so as to 
give the optimum heating performance and the air flow 
is sufficient to cool the heat exchanger. Ensure where 
vertical fins are installed they are also open and not 
restricting the air flow. 

  Check that there are no gas leaks  

  Check that the gas rate is correct using a meter. 

  Check injector pressure is correct. 

  Check temperature rise is correct to data plate. 

  Check the operation of the control and limit 

thermostats TR, SND, LM. 

  Check that the room thermostat operates the burner 

not the fan. 

  Check that the motor absorption is not more than 

stated on data plate. 

  Check that the flue venter and axial fan are working 

correctly. 

  Check that the fan runs on 3–4 minutes after the 

burner has shut down. 

  Check output corresponds to that on the data plate. 

  Check that there is no condensate in the flue 

gasses. 

 

 

MAINTENANCE

 

 
WARNING! 

It is a requirement that only qualified personnel are 
allowed to carry out installation commissioning or 
servicing. 
Before commencing any maintenance or servicing work 
the heater must be shut down and allowed to cool, and 
have the gas and electric supplies to it turned off at the 
supply cock and isolator respectively. 

In order to carry out analyses of the Flue gasses 
sample points must be made at the following 
dimensions See Diagram. 
 
 

 

COMBUSTION PRODUCT SAMPLING

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

1. 

Flue gas sampling point.

 

2. 

Combustion air sampling point.

 

 

 

CLEANING THE FLUE DISCHARGE AND AIR 
INTAKE PIPES 

The cleaning of the flue and air intake pipes consists of 
the removal of any dust and debris inside the pipes. 
 

 

CLEANING THE FAN 

The cleaning of the fan assembly consists of clearing 
any dust or debris from the fan blades, motor, and 
protective guard. 
 

 

FLUE VENTER CLEANING 

The cleaning of the flue venter consists of the cleaning 
of dust from the fan blades. 
 

 LIMIT 

THERMOSTAT 

Check the limit thermostat operation once a year by 
removing the TEST link and checking that the burner 
has extinguished. 

 

BURNER BAR CLEANING

 

The burner bar should be removed from its housing and 
the tube(s) should be cleaned with a brass wire brush 
and any dust or debris blown clear with a compressed 
air gun. Any tubes gaskets or seals that are damaged 
should be replaced. 
 

 

AIR FLOW FINS 

Ensure that the horizontal fins are set so as to evenly 
distribute the air in the area to be heated they should 
opened to a minimum of 45 degrees this will ensure that 
there is sufficient air flow over the combustion chamber 
and avoid nuisance over heat lockout .For this reason it 
is also important to ensure that the vertical louvres if 
fitted are also open and clean. 

 

Содержание RS UHA

Страница 1: ...it heaters TECHNICAL INFORMATION ASSEMBLY INSTRUCTIONS USE AND MAINTENANCE RS UHA RS UHA 2 RS UHA 4 BENSON HEATING LUDLOW ROAD KNIGHTON POWYS LD71LP U K August 2003 Benson Heating is a Division of Ben...

Страница 2: ...bly aware of the purpose of the manuals and the safety instructions In addition operators must be suitably trained in the use of the appliance so as to ensure its continued safe and efficient use Bens...

Страница 3: ...Heater serial number 3 Order reference date of order together with full installation details name and address 4 Details or symptoms of fault 5 Installers name and address Faulty parts must be returned...

Страница 4: ...ceipt of product 16 Transport 16 Dimension 17 FOR THE INSTALLER Installation 19 Wall bracket dimensions 19 Gas connection 22 Flue and combustion options 23 Electrical panel with circuit board 27 Elect...

Страница 5: ...type 6 7 models are equipped with two gas manifolds each manifold has an ignition electrode Control and safety thermostats The heater is controlled by three thermostats pre set to the following LM Li...

Страница 6: ...urer AIR HEATER Model Serial Number C PIN ountry C C ategory ode T Year ype N kW ominal heat INPUT N kW ominal heat OUTPUT A m ir Flow max 3 h Electrical Supply E W lectrical power Protection rating G...

Страница 7: ...ction 6 Flue manifold 7 Air discharge plenum with horizontal louvres 8 Burner compartment 9 Burner clams 10 Burner plate insulation 11 Gas injector 12 Combustion chamber 13 Gas manifold 14 Burner bars...

Страница 8: ...l louvres 8 Burner compartment 9 Burner clams 10 Burner plate insulation 11 Gas injector 12 Combustion chamber 13 Gas manifold 14 Burner bars 15 Ignition transformer 16 Left hand burner compartment 17...

Страница 9: ...350 420 350 mm Fan throw 10 14 18 26 32 35 37 m Electrical supply 230 V 50Hz 1ph Electrical power 0 155 0 165 0 225 0 345 0 440 0 600 0 670 kW Electrical protection 40 IP Gas category II 2H3P Install...

Страница 10: ...I Second stage gas valve 1 Two Stage version only C Fan capacitor FAN 1 Axial fan 1 FAN 2 Axial fan 2 type 5 F1 F2 Line fuses LF Green working light LL High temperature indication light LB Lockout ind...

Страница 11: ...econd stage gas valve 2 Two Stage version only C Fan capacitor FAN 1 Axial fan 1 FAN 2 Axial fan 2 FAN 3 Axial fan 3 type 7 F1 F2 Line fuse LF Green working light LL High temperature indication LB Loc...

Страница 12: ...reset EVG1 I Gas solenoid valve 1 EVG1 II Second stage gas valve 1 C Fan capacitor FAN 1 Axial fan 1 FAN 2 Axial fan 2 type 5 F1 F2 Line fuses LF Green working light LL High temperature indication LB...

Страница 13: ...EVG2 I Gas solenoid valve 2 EVG2 II Second stage gas valve 2 C Capacitor FAN 1 Axial Fan FAN 2 Axial Fan FAN 3 Axial Fan only type 7 F1 F2 Fuses LF Green working light LL High temperature indication L...

Страница 14: ...ey R Red G Green W White K Pink Y Yellow This wiring to be completed by the installer READ THE INSTRUCTION MANUAL BEFORE PROCEEDING WITH THE INSTALLATION 14 THIS HEATER IS NEUTRALLY SWITCHED ENSURE TH...

Страница 15: ...ed it will damage the heat exchanger and will invalidate the warranty on the heater SERVICING It is a requirement that only qualified personnel are allowed to carry out installation commissioning or s...

Страница 16: ...been reset this can be done by removing the plastic cap covering the reset button and pushing the reset replace cap The cause of the overheat should be investigated RECEIPT OF PRODUCT Delivery pre in...

Страница 17: ...1170 B mm 770 770 770 770 820 C mm 370 425 505 685 930 D mm 563 563 563 555 510 E mm 140 140 140 140 185 F mm 132 132 132 132 115 G mm 132 132 132 132 132 1 mm 100 1 100 1 100 1 100 1 100 2 2 mm 100...

Страница 18: ...18 100 male 132 185 510 315 150 male 115 820 130 A 860 225 C 15 530 225 15 Type 6 7 A mm 1720 1960 C mm 1270 1510 bsp Nett weight kg 171 205 Heater types 6 7 NOTE heaters type 7 have three fans 18...

Страница 19: ...e material adjacent to the heater or flue system must be so placed or shielded so that its surface temperature does not exceed 65 C The location chosen for the heater must allow for the fitting of an...

Страница 20: ...ontal flue options when using wall support brackets Type 1 2 3 4 Type 5 6 7 Diagram showing the installation limits for horizontal concentric flue options when using wall support brackets Type 1 2 3 4...

Страница 21: ...Examples of positioning in small and medium spaces Examples of positioning in large areas Installation heights and minimum distances from walls and ceilings 21 2500 3000 500 700 2500 3000 700 500 700...

Страница 22: ...itioned adjacent to and upstream of the union which must be sited outside the heater 5 Gas Pipe Customer supply WARNING When a LPG supply is used it is advisable to install a first pressure reducer cl...

Страница 23: ...separate pipes or with concentric pipes The flue pipe and combustion air inlet should be metal smooth bored pipe with a diameter of not less that both the flue and combustion spigot connections on th...

Страница 24: ...0 1 00 10 00 6 m 1 00 5 00 1 00 10 00 7 m 1 00 5 00 1 00 10 00 L2 100 MIN 400 L1 MAX 500 100 MIN 400 Only flue components and accessories supplied by the manufacturer should be used on installation In...

Страница 25: ...1 00 2 50 1 50 2 50 3 m 1 00 2 50 1 50 2 50 4 m 1 00 2 50 1 50 2 50 5 m 1 00 2 50 1 50 2 50 6 m 1 00 2 50 1 50 2 50 7 m 1 00 2 50 1 50 2 50 Only flue components and accessories supplied by the manufac...

Страница 26: ...2 m 0 10 00 3 m 0 10 00 4 m 0 10 00 5 m 0 10 00 6 m 0 10 00 7 m 0 10 00 Only flue components and accessories supplied by the manufacturer should be used on installation In installations where condensa...

Страница 27: ...ithin this manual The electrical supply isolator should be mounted adjacent to the air heater in an easily accessible position to allow for servicing isolation or emergency shut off Ensure that the El...

Страница 28: ...um Line Live Earth Supply Power current Fuse 1 conductor 2 conductor 2 V 50Hz kW A A mm2 mm2 1 230V 50Hz 0 155 6 6 3 5x20 mm T 1 5 1 5 2 230V 50Hz 0 165 6 6 3 5x20 mm T 1 5 1 5 3 230V 50Hz 0 225 6 6 3...

Страница 29: ...aneously If the gas line has not been correctly purged ignition may not take place at the first attempt resulting in lockout of the burner Reset button and repeat Before each attempt at ignition it is...

Страница 30: ...ue venter will start up activating the differential pressure switch The heater will pre purge the combustion chamber the electronic control box will supply the ignition electrode and the gas valve sim...

Страница 31: ...urer Natural Gas H G20 TYPE 1 2 3 4 5 6 7 Number of injectors 1 1 1 1 2 2 4 N Diameter of injector 310 410 480 555 500 540 450 mm 100 Gas supply pressure 20 mBar Head pressure high fire 12 0 13 0 13 0...

Страница 32: ...ng injector in the manifold heater Type 1 2 3 4 6 Replacing injectors 2per manifold for heater Type 5 7 Check that the size of the injector corresponds to that on the data plate 32 Check the size of t...

Страница 33: ...regulation Propane G31 Gas valve head pressure setting high fire Propane G31 When setting the gas pressure for propane high fire second stage contact SF should be closed the high fire pressure adjust...

Страница 34: ...FAN OPERATION AND LIMIT functions FAN OPERATION SND When the air near the sensor SND reaches the set temperature 30 C which is approximately 30 seconds after ignition the electrical contact closes and...

Страница 35: ...e or servicing work the heater must be shut down and allowed to cool and have the gas and electric supplies to it turned off at the supply cock and isolator respectively In order to carry out analyses...

Страница 36: ...It is recommended that the heat exchanger by cleaned once a year prior to the start of the heating season The following procedure should be carried out 3 4 5 6 7 Remove burner 1 from its housing after...

Страница 37: ...ty control box Change control box Faulty ionization electrode Check the electrode is not cracked or damaged Check the probe No ignition Flue venter not working No indication lights on Room thermostat...

Страница 38: ...and vertical if fitted louvres are sufficiently open see installation Check fan is operating correctly with sufficient air flow Faulty SND thermostat or faulty fan control l Change SND thermostat or f...

Страница 39: ...n probe Change ignition electrode Faulty solenoid Change solenoid Dirty gas filter Clean filter Control box will not reset Red light illuminated Faulty flame control module Change control module check...

Страница 40: ...BENSON HEATING LUDLOW ROAD KNIGHTON POWYS LD7 ILP Tel 01547 528534 Fax 01547 520399 www bensonheating com Benson Heating is a Division of Benson Climate Systems Ltd 04 08 03 Rev 2 Cod 034 MN 40...

Отзывы: