5.2 Flaring work
Main cause of gas leakage is defect in flaring work. Perform flaring work correctly in the following
procedure.
1. Pipe cutting
•
Cut the cooper pipe correctly with pipe cutter.
2. Burrs removal
•
Completely remove all burrs from the cut cross section of the pipe.
•
Put the end of the copper pipe downward to prevent burrs from dropping in the pipe.
3. Putting nut on
•
Remove flare nuts attached to indoor and outdoor units, then put them on pipe having completed
burr removal.
(Not possible to put them on after flaring work).
•
Flare nut for R410A pipe may differ from R22 pipe depending on the diameter of pipe.
4. Flaring work
•
Perform flaring work using flaring tool as shown below.
Outside diameter
A (mm)
Flare tool for R410A
clutch type
Conventional flare tool
Clutch type
Wing nut type
Ø6.35mm
0 to 0.5
1.0 to 1.5
1.5 to 2.0
Ø9.52mm
0 to 0.5
1.0 to 1.5
1.5 to 2.0
Ø12.7mm
0 to 0.5
1.0 to 1.5
2.0 to 2.5
Ø15.88mm
0 to 0.5
1.0 to 1.5
--
Firmly hold copper pipe in a die in the dimension shown in the table above.
5. Check
•
Compare the flared work with the figure below.
•
If flare is noted to be defective, cut off the flared section and perform flaring work again.
5
Indoor/outdoor units connection finishing and
test run
Содержание BKFO 160
Страница 1: ...Air conditioner inverter Installation manual BKFO 160 EN IT ...
Страница 46: ......
Страница 47: ...Prodotto da Arcelik A S Karaagac Cd No 2 6 34445 Sutluce Beyoglu Istanbul Turchia ...
Страница 48: ...www beko com ...