28 | Start Line MT 601 D | Initial commissioning
en
4.4
Power socket
!
MT 601 D must not be connected to the power
supply unless its voltage is the same same as that
specified on the rating plate.
1. Check to ensure that power supply is at the same
voltage as specified on the rating plate.
2.
Check the usual standard for machines and ensure
that the power connector and power port on cus-
tomer premises both comply with that standard.
3.
Connect up to power supply.
4.
Connect switch connector of wheel-guard cover.
Fig. 8:
Connect switch connector of wheel-guard cover
2.
Attaching the wheel-guard hood and hood bracket.
Fig. 6:
Fitting the wheel-guard hood
3.
Install wheel-guard hood in support and tighten the
screw.
4.
Install support bracket 2, then install the plate as
shown in the following Figure.
Fig. 7:
Installing the support bracket
4.5
Checking direction of rotation
1.
Check whether the MT 601 D is properly connected
to the mains.
2.
Switch on the MT 601 D at the on/off switch.
3.
Close the wheel-guard hood.
Flange shaft rotates.
!
If flange shaft does not rotate, press button <???>.
i
If the direction of rotation is incorrect the MT 601 D
comes to an immediate halt and the error message
ERR 3
is displayed.
4. Check direction of rotation of flange shaft.
i
The correct direction of rotation is indicated by a label
on the right side of the MT 601 D.
4.6
MT 601 D calibration
!
Calibration must be performed after initial commis-
sioning.
1. Calibrate the flange.
2.
Calibrate rim-distance gage.
3.
Calibrate MT 601 D.
4.
Perform reference measurement.
i
The calibration is described in the section "Calibra-
tion".