10
Initial Operation
Cartridge Installation
1.
Open cartridge access door in the rear of the unit by
pushing the door latch down.
2.
Remove a new Pretreatment cartridge (part number
D50230 or D50231) from its plastic bag.
3.
Wet the o-rings on both end caps.
4.
Press the upper end cap into the upper right position
until it bottoms out.
5.
Lower the cartridge and insert the lower end cap into
the lower socket until it is firmly seated.
6.
Repeat steps 1 - 5 with the EASYpure High Purity/Low
TOC or Ultrapure cartridge, placing it in the left-hand
position.
7.
Close cartridge access door.
Storage Reservoir Filling and Cartridge Rinse
Up
To fill the reservoir:
1.
Remove the molded plastic Ventgard cap.
2.
Carefully pour pretreated feedwater into the reservoir
until the water is level with the top of the sight gauge
on the front of the unit. Replace the Ventgard cap.
3.
Plug power cord into the power entry module on the
left-hand side of the rear of the unit and plug into a
live outlet. Turn on power entry module switch.
4.
Press “START” and open draw-off valve.
5.
Rinse one complete reservoir volume of water through
the cartridges to drain.
6.
Remove a new 0.2 micron filter and bell assembly
from its bag and insert it into the Luer fitting. Gently
turn it clockwise until it is fully seated in the Luer fit-
ting.
7.
Refill the reservoir with pretreated water.
8.
Flush second reservoir volume of water through the fil-
ter.
NOTE
The upper end cap is the one with the right-an-
gle turn and the two flanges. The lower end cap
extends straight out from the cartridge. (See
Figure 3.)
NOTE
The two flanges on the end cap should be able
to slide down on each side of the keyway wall.
NOTE
Cartridge rinse up procedure must be followed
after each cartridge and/or filter replacement.
NOTE
In the event that you overfill the feedwater res-
ervoir, allow the excess water to drain from the
reservoir through the overflow drain tubing be-
fore replacing the Ventgard cap. This will pre-
vent wetting the filter element.
Initial Operation