General Information

The ventilator should only be installed by a trained 
heating and air conditioning technician. These 
instructions serve as a guide to the technician installing 
the ventilator package. They are not intended as a step-
by-step procedure with which the mechanically inclined 
owner can install the package.
The ventilator housing is shipped in one carton which 
contains the electrical harness, miscellaneous hardware 
and installation instructions.

Unpacking

Upon receipt of the equipment, be sure to compare the 
model number found on the shipping label with the 
accessory identification information on the ordering and 
shipping document to verify that the correct accessory 
has been shipped.
Inspect the carton housing of each ventilator as it is 
received. Before signing the freight bill, verify that all 
items have been received and that there is no visible 
damage. Note any shortages or damage on all copies 
of the freight bill. The receiving party must contact 
the last carrier immediately, preferably in writing, 
requesting inspection by the carrier’s agent. Concealed 
damage not discovered until after loading must be 
reported to the carrier within 15 days of its receipt.

Description

The ventilators are designed to be used with Bard 2 − 5 
ton single stage wall mount gas electric units. They are 
electromechanical vent systems designed to provide 
fresh air to meet indoor air quality standards with built 
in exhaust provisions.

Features

•  One piece construction: Easy to install with no 

mechanical linkage adjustment required.

•  Exhaust air damper: Built in with positive closed 

position. Provides exhaust air capability to prevent 
pressurization of tight buildings.

•  Actuator motor – 24 volt, power open, spring return 

with built-in torque limiting switch.

•  Solid state control board – can be used for ON/OFF 

or 2-10VDC operation. Timed pre-purge feature to 
provide increased ventilation before occupancy. 
Potentiometers used to set blade position for ON/
OFF ventilation amount.

•  Provides up to 75% of outside air.

Sequence of Operation

When no ventilation call is present, ventilation damper 
remains closed and conditioned air is 100% return air 
(see Figure 1 on page 4).
On a call for ventilation, commercial room ventilator 
(CRV) opens to position set by minimum position 
potentiometer and energizes comfort air blower (see 
Figure 2 on page 5).

GENERAL INFORMATION 

Commercial Room Ventilator Model Nomenclature

WGCRVS  – 

3  C 

Revision

Commercial Room Ventilator

Chassis Size

3 – W24-36G Models
5 – W42-60G Models

Содержание WGSCRVS-3C

Страница 1: ...Manufacturing Company Inc Bryan Ohio 43506 www bardhvac com Manual 2100 757 Supersedes NEW Date 12 7 21 For Use with Bard Single Stage W G4 Units Commercial Room Ventilator with Exhaust and CO2 Modul...

Страница 2: ...for Blower Operation w o Ventilation 4 Figure 2 Call for Ventilation 5 Figure 3 Removal of Vent Option Panel 6 Figure 4 Loose Piece Wire Harness Plug Install 7 Figure 5 Ventilator Installed in Unit 8...

Страница 3: ...reported to the carrier within 15 days of its receipt Description The ventilators are designed to be used with Bard 2 5 ton single stage wall mount gas electric units They are electromechanical vent s...

Страница 4: ...Manual 2100 757 Page 4 of 17 FIGURE 1 Call for Blower Operation without Ventilation...

Страница 5: ...Manual 2100 757 Page 5 of 17 FIGURE 2 Call for Ventilation...

Страница 6: ...it see Figure 3 3 Remove and save existing unit air filter and screw from front center grille see Figure 5 on page 8 for screw location 4 Remove and discard the exhaust cover plate 5 Replace the exhau...

Страница 7: ...ntrol box 9 Connect leads with fork terminal to corresponding points on terminal strip See wiring diagrams later in this manual or on ventilator Plug connector into corresponding hole in filter rack s...

Страница 8: ...NSET Plug mating plug from WGCRV into plug in filter partition When installing WGCRV position so that hole in front lip is centered over hole in condenser grill to insert a self drilling screw Mist El...

Страница 9: ...ntrol board with blade positioning potentiometers along with an input for a 2 10V input signal see Figure 6 on page 10 Adjustable potentiometers PP Potentiometer setting This potentiometer can be used...

Страница 10: ...he motor directly from the device providing the 2 10VDC modulating signal The gray wire connected to CO2 V IN on the control board must be spliced with the white wire ran to the damper motor V OUT on...

Страница 11: ...TO CHANGE ANY SETTINGS WITH THE SIDE BUTTONS TO LOCK THE CO2 DIP SWITCHES MUST BE POSITIONED AS SHOWN FOR PROPER OPERATION MIS 4025 C Settings Recommended Default RON RELAY ON SET POINT 725 ROF RELAY...

Страница 12: ...Manual 2100 757 Page 12 of 17 Fresh Air CFM Fresh Air CFM Fresh Air CFM...

Страница 13: ...Manual 2100 757 Page 13 of 17 Fresh Air CFM Fresh Air CFM Fresh Air CFM...

Страница 14: ...Manual 2100 757 Page 14 of 17 Fresh Air CFM Fresh Air CFM Fresh Air CFM...

Страница 15: ...and connect to N C fire alarm circuit if emergency shutdown required 3 2 Wire required for dehumidification models only 1 For vent operation thermostat must be configured for programmable events per d...

Страница 16: ...to the up position Connect wire to lower U terminal for vent operation Only applies to 8403 090 1 Jumper needs added when using 8403 047 humidistat RED WHITE BLACK WHITE ORANGE BROWN WHITE GRAY CRVS...

Страница 17: ...2 jumper is used from A to G Move Brown White wire landing from COM to NC if CONTROL PANNEL 1 40 43 9 PIN MOLEX PLUG FEMALE 9 PIN MOLEX PLUG MALE 39 2 1 4056 266 B 1 BLUE BROWN WHITE BROWN WHITE BROW...