Installation • Commissioning
80
Power Panel C-Series User's Manual V1.00
25°
25°
Figure 24: Power Panel - Mounting orientations
Caution!
The maximum permitted ambient temperature can be found in the technical data for the respective
Power Panel device.
3 Commissioning
The Power Panel comes with Automation Runtime as default. Automation Runtime must first be installed in order
to be able to operate the Power Panel. There are 3 methods available:
•
AR transfer over the network with DHCP server
•
AR transfer over the network without DHCP server
•
USB stick - remote install structure
AR transfer over the network with DHCP server
See the AS help documentation
AR transfer over the network without DHCP server
•
Connect the Power Panel to the network
•
Start the Power Panel
•
Create a new project with Power Panel in Automation Studio
•
Open the browse dialog box in online settings
•
Right-click on Power Panel with IP 0.0.0.0 and select "Set IP Parameters"
•
The settings can be taken from the following example: