4 Preparation for operation
4.1 Installation site requirements
The installation location of the ultrasound bath must meet the fol-
lowing conditions:
• The installation surface must be horizontal, firm and dry.
• The load-bearing capacity must be sufficient for the ultrasound
bath with the sonication liquid.
• Adequate ventilation must be ensured. The air supply under the
bottom of the unit may not be obstructed. If a sound proof box
is used, it must also ensure sufficient ventilation.
• A water connection should be available nearby to fill the ultra-
sound bath. A basin must be available to drain or pour out the
sonication liquid.
4.2 Fitting ball valve
If supplied, fit the enclosed ball valve, the hose grommet and the
hose as described in the assembly instructions included with the
ball valve.