2.2 OPERATING PROCEDURE
Follow the steps as outlined below:
2.2.1 Connection Procedure Connect Battery Capacity
Analyzer (600B) to Battery Under Test (BUT). Connect the +ve
terminal of 600B to +ve terminal of Battery. Connect -ve
terminal of 600B to -ve terminal of Battery. The 600B will be
powered by the BUT. On Power up, 600B performs a self test
by turning on the 7 segments, LEDs one after another & finally
flashing the version number.
Caution: Do not connect the +ve terminal of 600B to -ve
terminal of BUT and -ve terminal of 600B to +ve terminal of
BUT. By doing so, the ‘Reverse Polarity’ LED glows as shown.
2.2.2 Selecting Ah Capacity
Press the 'Ah Range' key. The select LED glows as shown.
The display will show the last selected/stored Ah value.
(Power ON default value is 7 Ah)
To change the value, press the key again. Display shows new
value. Keep on pressing till the desired Ah is obtained.
To Lock the Ah capacity, either press any key OTHER than the
Ah Range key OR wait for about 10 seconds. Your selected Ah
value will automatically get locked and is indicated by the
glowing of 'Locked' LED.