Step 3: Construction sealant application (Sikabond or equivalent)

In order to avoid leakage between the frame and the wall, construction 

sealant shall be applied on the back side of the frame:

• 

 Remove the channel penstock from the wall (first remove the nuts of the anchor bolts). 

• 

 Apply construction sealant all around the perimeter of the frame, where it will be in  

 contact with the wall.  

 Sikabond (200 ml/m) or equivalent construction sealant shall be used (See figure 14).  

 Be sure not to get sealant on the seals, guides, and/or stem, as this may cause leakage  

 damage. 

  

• 

 Re-install the penstock on the wall and tighten both anchor bolts.

Step 4: Final installation of channel penstock

• 

 Drill and install the rest of the anchor bolts (see Figure 15).

CAUTION!: 

If the channel penstock is not completely in contact with the wall, do not over-tighten the anchor bolts. Over tightening may 

bend or distort the frame. If the wall flatness and levelness is according to the specified standards, the construction sealant 

will fill in the remaining void (see Figure 16).

• 

 Apply construction sealant around the frame in order to fill in any existing gap between the wall and the frame (this step is  

 only for esthetics). Wipe away the excess sealant to leave a smooth finish.

Page 8/12   

MI ChannelPenstock772 rev AB August 2014 GB

INSTALLATION & MAINTENANCE INSTRUCTIONS - ORIGINAL VERSION

AVK CHANNEL PENSTOCKS

SERIES 772/71

Construction Sealant

(Sikabond 200ml/m)

Back Side of Frame

(side in contact with the wall)

Void

Do not overtighten

anchor bolt

Concrete

wall

Figure 16

Figure 15

Figure 14

Содержание 771 Series

Страница 1: ...llation and maintenance Penstocks are usually of large dimensions and heavy Appropriate lifting devices must therefore be used for secure handling Penstocks shall be lifted from the main frame or from the yoke if applicable Holes are available for lifting eyes Slings can also be used Never lift the penstocks in inverted positions Do not use stems slides or actuators as lifting points Passing throu...

Страница 2: ...lease refer to the notes on the General Arrangement Drawing 5 1 1 INSTALLATION PROCEDURE Step 1 Concrete construction inspection The concrete construction shall be flat level and plumb and shall be in accordance with the ACI 117 06 standard If necessary use non shrink grout in order to meet the specified standard The minimum concrete strength shall be 3 000 PSI 20 7 MPa Step 2 Align the channel pe...

Страница 3: ...ent Side Bolt Side Centering Fitting Frame Guide Channel SideWall Second Phase of Concrete Bottom Leveling Bracket Field Adjustment Bottom Bolt Adjust the bolts so the frame invert is flush with the invert of the channel Frame Invert Channel Invert Second Phase of Concrete Figure 2 9 0 Wall Recess Field Adjustment Side Bolt Side Centering Fitting Frame Guide Channel SideWall Second Phase of Concre...

Страница 4: ...ges or with a bad surface condition in order to avoid any damage to the bottom seal 5 2 INSTALLATION FACE MOUNTED IN EXISTING CHANNEL Required materials For the face mounted in existing channel FM mounting option the channel penstock is installed by means of mechanical anchor bolts Hilti Kwilt 3 or equivalent All the gaps shall be grout filled afterwards and shaped in order to get a smooth transit...

Страница 5: ... All face mounted channel penstocks incorporate bottom and lateral mounting brackets For smaller sizes typically under 60 the channel penstock includes lateral flexible brackets as seen in Figure 8 that require no field adjustment For bigger sizes typically over 64 the channel penstock includes field adjustment brackets In order to adjust the bracket the following steps shall be followed see Figur...

Страница 6: ...ON Make sure not to get grout or any other foreign material on the seals guides or stem as this may cause leakage or damage Page 6 12 MI ChannelPenstock772 rev AB August 2014 GB INSTALLATION MAINTENANCE INSTRUCTIONS ORIGINAL VERSION AVK CHANNEL PENSTOCKS SERIES 772 71 Grout Fill Frame Invert Lateral Bracket Void Grout Fill Anchor Bolt Lateral Bracket Bottom Bracket Frame Invert Frame Figure 10 Gro...

Страница 7: ...plumb and shall be in accordance with the ACI 117 06 standard If necessary use non shrink grout in order to meet the specified standard The minimum concrete strength shall be 3 000 PSI 20 7 MPa The wall surface shall be dry Step 2 Pre installation of the channel penstock Position the channel penstock against the wall and line up with the opening See Figure 12 The slide shall be in the closed posit...

Страница 8: ...Drill and install the rest of the anchor bolts see Figure 15 CAUTION If the channel penstock is not completely in contact with the wall do not over tighten the anchor bolts Over tightening may bend or distort the frame If the wall flatness and levelness is according to the specified standards the construction sealant will fill in the remaining void see Figure 16 Apply construction sealant around t...

Страница 9: ...tion to assure proper direction of the slide travel according to the motor operation switch open close Special attention should be taken when the slide is almost fully open or fully closed If the actuator does not stop once the fully open or fully closed position is reached stop immediately and adjust the limit and torque switches Refer to motor manual 6 2 OPERATION CAUTION Do not force the operat...

Страница 10: ...er before operating the channel penstock Operating the slide with dry seals may damage the seals Additionally more torque may be required to operate the channel penstock 7 1 1 SPARE PARTS AVK does not recommend stocking any spare parts by the owner of the equipment as the channel penstocks are designed for a very long life cycle If a repair part is required please contact an AVK representative and...

Страница 11: ...4 and 7 from the slide and remove retainers items 2 lateral HMWPE guides items 4 and front HMWPE guides items 5 Step 7 Remove side seals item 8 and replace it by the new seal Note 1 Apply glue where the bottom seal and side seals join Note 2 After installing the new seal apply grease on it to ease operation 7 2 3 BOTTOM SEAL REPLACEMENT FIGURE 18 Step 8 Remove bolts and nuts items 10 and 12 and re...

Страница 12: ...ose anchor bolts Tighten anchor bolts Incorrect anchor bolts Check the General Arrangement Drawing and make sure the right anchor bolts have been installed Leakage through the side seals Damaged seal Replace seal Foreign material trapped between frame invert and slide Remove the foreign material Check if there is any damage to the seal Damaged seal Replace seal Misaligned stem extension stem guide...