Step 3: Grout fill
Grout fill the remaining voids (See Figure 8), both at the bottom (See Figure 9) and laterals of the penstock (See Figure 10).
Remember that the objective of the grout fill is twofold:
•
Fill the voids between the frame, frame invert and the channel.
•
Make a smooth transition for water flow. Therefore, the grout shall be built-up to the level of the frame as shown in Figures
9 and 10.
CAUTION! Make sure not to get grout or any other foreign material on the seals, guides or stem as this may cause leakage or
damage.
Page 6/12
MI ChannelPenstock772 rev AB August 2014 GB
INSTALLATION & MAINTENANCE INSTRUCTIONS - ORIGINAL VERSION
AVK CHANNEL PENSTOCKS
SERIES 772/71
Grout Fill
Frame Invert
Lateral Bracket
Void
Grout Fill
Anchor Bolt
Lateral Bracket
Bottom Bracket
Frame Invert
Frame
Figure 10
Grout Fill
Frame Invert
Lateral Bracket
Void
Grout Fill
Anchor Bolt
Lateral Bracket
Bottom Bracket
Frame Invert
Frame
Figure 11
Bottom Anchor Bolts
Laterall
Anchor Bolts
Figure 8
Grout Fill
Figure 9