3. INSTALLATION

Safety guidelines: please refer to the installation manual for all safety instructions.
To perform the installation, please download the installation manual at the following address: www.avidsen.com 

Overview:

The cables used must be appropriate for outdoor use (such as H07RN-F for example). The cable run between the two posts must comply with applicable 
standards (NFC 15-100). The power cable of the opposite geared motor must run 80cm deep with red warning mesh.

Motors

Inner side of the property

Flashing light

1

2

3

4

5

List of cables:

Connection

Cable

Max length

1

230VAC power line

Cable 3 x 2.5mm2 (more than 30m long) 

Cable 3 x 1.5mm2 (less than 30m long)

Unlimited

2

Flashing light

Cable 2 x 0.5mm2

15m

3

Secondary motor

2 x 1.5mm² cable

10m

4

Reception photocell (RX)

4 x 6/10 cable

10m

5

Transmission photocell (TX)

4 x 6/10 cable

10m

The installation is a 4-step process:
1. Installation of the motors onto the pillars and gate, and of the flashing light (the main motor is installed on the pillar where the power comes from).

2. Electrical connection:
 

 

- of the secondary motor to the electronic card (in the main motor)

 

 

- of the flashing light to the electronic card (in the main motor)

 

 

- of the photocells to the electronic card (in the main motor)

 

 

- connection of the transformer to the mains. This connection must be performed by qualified personnel (electrician, etc.)

3. Adjustments and operation:

Note: Only switch on the system once all connections have been made.

- Read the installation manual chapter on simple adjustments.
- Launch the movement self-learning programme (press "+" for 3 seconds)
- Programme the remote controls:
 

 

- press "-" for three seconds, press "OK", press the remote control button to be memorised, repeat the operation for each remote control

- Choice of operating mode:
By default, automatic closing is deactivated. To activate it:
 

 

- Press PROG for three seconds, press "OK", press "+", press "OK"

4. Operational testing: To familiarise yourself with the automatism and ensure it operates properly, read the chapter on usage and conduct operational tests (open/
close, initiate obstacle detection, cut the photocell beam). Upon completion of these tests, you may have to modify certain settings (e.g. motor power).

4. DECLARATION OF CONFORMITY

Avidsen declares that the equipment complies with the essential applicable requirements of RED Directive 2014/53/EU.
Directive 2014/35/EU: (protection of users’ health and safety)
Directive 2014/30/EU: (protection requirements relating to electromagnetic compatibility).
Directive 2014/53/EU: (efficient use of the radio spectrum, in order to avoid harmful interference).
The full declaration of compliance is available on the website www.avidsen.com

Tours, 02/11/2020
Alexandre Chaverot, CEO

Pour en savoir plus : 
www.quefairedemesdechets.fr

Avidsen 

19 avenue Marcel Dassault - ZAC des Deux Lions - 37200 Tours - France 

Отзывы: