Atag Premier E-HR 24 Скачать руководство пользователя страница 22

Installation instructions E-SHR series page 22

13 Maintenance

Maintenance or changes to the unit may only
be carried out by an authorised technician.

13.1 The frequency of maintenance

We advise to carry out an inspection to the boiler every
two years and an overhaul every four years. When doing
this the circumstances of the boiler’s location must be
taken into account, From this one can determine whether
to deviate from this advice.

13.2 Maintenance activities

If it is necessary to clean the boiler the following actions
to the following components must be carried out:

The air unit (casing of the boiler)
Dirt which is sucked in by the air supply pipe will end up
at the bottom of the casing. This dirt can be cleaned with
a cloth with a simple (non-abrasive) cleaning agent.

The burner ceramic bricks and heat exchanger
These components should only be cleaned if it is
determined that the maximum Pa is no longer obtained as
described in chapter 12.1.

The fan unit must be removed in order to be
able to inspect the heat exchanger.

In this case the following actions must be carried out:
- close the gas valve and isolate the boilers electrical

supply;

- loosen the nut of the gas pipe under the gas block;
- loosen the small crosshead screw on the red

electrical connection adaptor of the gas block;

- remove the electrical connection plug from the fan

motor;

- loosen the front crosshead screw of the black plastic

air inlet damper;

- after this turn the two clamping rods ¼ turn and remove

them by pulling them forward;

- slightly lift the fan unit and remove it towards the front

of the heat exchanger;

- the fan unit and the air inlet damper can be checked

for contamination and if necessary cleaned;

- now remove the burner ceramic bricks by slightly

lifting them upward and removing them in the same
direction as the heat exchanger fan unit;

- the burner ceramic bricks and the heat exchanger can

be cleaned by means of a soft brush;

Do not flush the heatexchanger through with
water

Refitting of the components is done in reverse.

12.2 Checking the CO

2

The CO

2

 percentage is factory-set. This has to

be checked during check up, service and
error intervalls.

- remove the black cover from the gas valve by means

of unscrewing the by paint sealed screw.

- put the boiler into operation by means of the service

chapter as described in chapter 10.3;

- place the lance of the CO

2

 gauge in the location

according to figure 14;

adjustment screw CO

2

  

figure 15

measuring point for CO

2

  

figure 14

- adjust to maximum load by means of the “+” key;
- ending the manual selection is done by pressing the

“-” key until the minimum load is shown. After pressing
this key again the text 

 is shown which means

that the selection is off.

- adjust the CO

2

 percentage according to table 12. The

CO

2

 percentage can be adjusted by means of the

adjustment screw according to figure 15.

- replace the black cover and tihgten it with the screw.

Содержание Premier E-HR 24

Страница 1: ...INSTALLATION SERVICING INSTRUCTIONS 8G 51 18 01 07 04 We reserve the right to make changes CE PIN 0063AS3538 These instructions to be retained by user ...

Страница 2: ...essure is to low 0 7 bar FILL indication remains continuously visible the boiler is taken out of operation The installation needs to be topped up Water pressure is to high 2 8 bar HIGH indication remains continuously visible the boiler is taken out of operation The installation pressure needs to be decreased by draining water Operation indication in the first display position Mode key Selecting ch...

Страница 3: ...ot water supply 16 10 Commissioning the boiler 17 10 1 Central Heating system 17 10 2 Hot water supply 17 10 3 Adjustments 17 11 Isolating the boiler 20 12 Commissioning 21 12 1 Checkingforcontamination 21 12 2 Checking the CO2 22 13 Maintenance 23 13 1 Thefrequencyofmaintenance 23 13 2 Maintenanceactivities 23 13 3 Further checks 23 14 Technicalspecifications 24 15 Diagram showing various parts o...

Страница 4: ...competent person eg Members of CORGI and in accordance with the current Gas Safety Regulation Failuretoinstallappliancecorrectlycouldlead toprosecution In addition to the above regulations this appliance must be installedincompliancewiththecurrentIEERegulations the Building Standards Scotland Consolidation Regulations Regulations and bye laws of the Local Water Authority and theCurrentHealthandSaf...

Страница 5: ...ly topped up or filled up installation this programtakescareoftheremovalofanypresentairinthe boiler Inthiscasethecontrolwillcheckthewaterpressure and if it is too low will report this on the display The boiler anticipates the heat requirement of the central heatinginstallationorthehotwatersupply Asaresultthe boiler will adjust its capacity to the installation and will switch on less often which me...

Страница 6: ...the boilers rear wall Dimensions see figure 4 table 1 t i n u f o e p y t 5 1 R H S E 4 2 R H S E T 4 2 R H S E T 5 3 R H S E A t h g i e h m m 0 5 6 0 5 6 0 5 6 B t h g i e h k n a t n o i s n a p x e h t i w m m 0 7 8 C h t d i w m m 0 0 5 0 0 5 0 0 5 D h t p e d m m 5 9 3 5 9 3 5 9 3 E t s u a h x e s a g e u l f e d i s t f e l m m 5 3 3 5 3 3 5 3 3 F y l p p u s d n a t s u a h x e s a g e u ...

Страница 7: ...astening and supporting positions in mm figure 3 54 332 619 5 337 supporting point 52 220 Two points are located on the back of the boiler which can be used in situations in which the boiler is being suspended on a frame In addition the dimensions of the drilling holes for fastening the boiler are shown The dimensions of the drilling holes are also shown on the template ...

Страница 8: ...tic sealing caps from the pipes contaminated testing water can be released It is advisable to spray clean all of the unit s connectingpipesand ortospray clean blow clean the installation before connecting it to the unit connection diameters table 2 f w g k r c boiler pipes bottom Premier figure4 t i n u f o e p y t R H E 5 1 R H E 4 2 R H E T 4 2 R H S E T 5 3 m e t s y s s a g e u l f y l p p u s...

Страница 9: ...detected then the controlwillrepeatedlytrytoachievewaterflow andifthis does not work then the boiler will switch off available water flow at full load table 3 external installation pump in series figure 6 t i n u f o e p y t p m u P e p y t e t a r w o l f r e t a w D C 0 2 T e l b i s s i m r e p n o i t a l l a t s n i e c n a t s i s e r n i m l h l a P k r a b m 5 1 R H S E 0 5 0 2 S P U 3 0 1...

Страница 10: ...ess steel plate exchanger for producing domestic hotwater Theboilerdoesnothaveahotwaterstoreand in case of a demand for hot water the boiler will heat the sanitary water flowing through the plate heat exchanger up to 63 C instantanious The water mains installation must comply with the water BYE laws In regions with a water hardness value higher than 15 D calcium deposits should be removed from the...

Страница 11: ...gs into the adaptor 1 Please remove both flue gas test nipples items 2 3 Make flue or fitting connection Re connect both flue gas test nipples Flue systems must comply with the current regulations It is essential that in practice products of combustion dischargingfromtheterminalcannotre enterthebuilding or any other adjacent building through ventilators windows doors othersourcesofnaturalormechani...

Страница 12: ...lcondensationcollectiondeviceinthe outlet system is surplus to requirement The appliance produces a white wisp of condensation This wisp of condensation is harmless but can be found to be unpleasant particularly in the case of outlets in outside walls For further information regarding the supply range of the exhaust and supply system please contact the country distributor 6 9 Air supply ItisNOTnec...

Страница 13: ...00 The ATAG room thermostat and controls must be connected to their allocated connections All other types or makes of room thermostats or controls which are used must have a Volt free contact 230 Volts for external pump mains power supply 230 Volts for external control 230 Volts internal or external three way valve motor and cylinder sensor ATAG room thermostat On off thermostat or control Volt fr...

Страница 14: ...Installation instructions E SHR series page 14 electrical connecting diagram figure 12 ...

Страница 15: ...re overshoot On a call for hot water supply the T set value of central heating return water temperature is monitored Depending on the amount of sanitary water which is withdrawn from the DHW facility the central heating return water temperature from which the input is adjusted will vary 8 1 Explanationofthefunctionkeys Key functions from the and the extensive indication are Central Heating program...

Страница 16: ...ional lampsoff Connect the mains filling loop not supplied Open the cold water supply tap on the filling loop and allow the system to fill slowly Theboilerhasanautomaticventwhichremovestheair which is present Bring the installation pressure up to between 1 5 and 2 0barafterallradiatorsandpipeshavebeenvented Close the mains filling loops main inlet tap remove filling loop and cap supplies Activate ...

Страница 17: ... the boiler will start the burner 10 2 Hotwatersupply Providedthereisaheatrequirementfromthecylinderthe hot water program will be put into operation by means of the key hot water program 10 3 Adjustments In the Control Tower a number of adjustments can be made Theseadjustmentscanbefedineasilybymeans of the keys on the boiler However a distinction is made between adjustments which are done by the u...

Страница 18: ...whicherrordatacanberetrieved user adjustment possibilities table 7 s t n e m t s u j d a r e t e m a r a p r e s U p e t S n o i t p i r c s e d y r o t c a f e g n a r 1 g n i t a e h l a r t n e c p m e t r e t a w w o l f m u m i x a m C 5 8 C 0 9 0 2 2 m e t s y s g n i t a e h l a r t n e c f o e p y t 1 0 4 1 1 0 s r o t c e v n o c g n i t a e h r i a s r o t a i d a r r e t a w w o l f x a...

Страница 19: ...a m x a m n i m 9 4 y t i c a p a c p m u p x a m g n i t a e h l a r t n e c 0 0 1 0 0 1 0 4 9 8 e c a f r e t n i g n i t t e s s s e r d d a 0 7 1 1 e r a p s 0 t a t s o m r e h t s u b G A T A e e S t a t s o m r e h t Q n i a r B G A T A 8 1 e g a p n o Informationchapter After feeding in the access code the information can be read out according to table 9 In order to select the informationc...

Страница 20: ...herwisereturningtothe Good read outautomatically occursafter20minutesintheeventthatnomorekeyshave beenused installer service possibilities table 10 installer error possibilities table 11 r e l l a t s n i e d o m r o r r E p e t S n o i t p i r c s e d e u l a v 1 r e b m u n r o r r e 2 t i n u s u t a t s g n i t a r e p o 3 1 T e r u t a r e p m e t r e t a w w o l f C 4 2 T e r u t a r e p m e...

Страница 21: ... 1 Checkingforcontamination In order to be able to check the boiler for contamination in the following running years it is advisable to measure the maximum air displacement in the boiler when putting the boiler into operation This value can be diffe rent with each type of boiler In order to be able to measure this value the following operations must be carried out inordertoentertheservicechapterfe...

Страница 22: ...rom the fan motor loosen the front crosshead screw of the black plastic air inlet damper afterthisturnthetwoclampingrods turnandremove them by pulling them forward slightly lift the fan unit and remove it towards the front of the heat exchanger the fan unit and the air inlet damper can be checked for contamination and if necessary cleaned now remove the burner ceramic bricks by slightly lifting th...

Страница 23: ...the condensate tray of the heat exchanger where the siphon is fixed pullthesiphondownwardsuntilitisreleasedfromthe condensate tray pullthedrainpipeofthesafteyvalveoutofthesiphon turn the siphon carefully out of the boiler clean the siphon and re fill with water Refitting is done in reverse order 13 3 Furtherchecks Checking the ionisation current ionisation determines if there is a flame present wi...

Страница 24: ...0 3 2 9 2 5 0 6 N E o t g n i d r o c c a n o i t c e t o r p f o e e r g e d 0 4 P I 4 4 P I y r o g e t a c e u l f y b 3 3 B 3 2 B t e n t h g i e w g k 7 3 7 3 7 3 0 4 d e s a b H C y t i c a p a c r e t a w l 5 3 5 3 5 3 5 d e s a b W H D y t i c a p a c r e t a w l 5 0 7 0 H C e m i t n u r r e v o p m u p n i m 5 1 5 1 5 1 5 1 W H D e m i t n u r r e v o p m u p c e s 0 2 0 2 m u m i n i m ...

Страница 25: ...ldwaterpipe E SHR T W hotwaterpipe E SHR T T1 flowsensor T2 returnsensor T3 DHWsensor E SHR T T5 flue gas sensor if fitted T10 Airboxtemperaturecontrol P1 waterpressuresensor 15 Diagram showing various parts of the boiler boiler diagram to be used in conjunction with figure 17 page 26 figure 16 A W G K R C P1 8 3 15 7 14 2 1 4 5 6 11 13 12 10 9 17 ...

Страница 26: ...e 25 figure 17 10 ControlTower 11 water filter return central heating 12 three wayvalve 13 circulationpump 14 flue gas discharge 15 combustion air supply 16 type plate 17 expansionvessel G gas pipe A flow connection central heating R returnconnectioncentralheating C condensationpipe K coldwaterpipe E SHR T W hotwaterpipe E SHR T T1 flowsensor T2 returnsensor T3 DHWsensor E SHR T T5 flue gas sensor...

Страница 27: ...2 expansionvessel 3 outside sensor ARV12 4 drainpoints 5 ATAG room thermostat 16 Example diagrams for connecting the boiler 16 1 Radiatorinstallationwithoutthermostatvalves connecting of the boiler to a radiator installation without thermostat valves figure18 1 2 3 4 5 ...

Страница 28: ...nwiththermostatvalvesonly connecting of the boiler to a radiator installation with thermostat valves only figure19 1 2 3 4 5 6 1 ATAGPremierboiler 2 expansionvessel 3 outside sensor ARV12 4 drainpoints 5 ATAG room thermostat 6 by pass trv thermostaticradiatorvalve trv trv ...

Страница 29: ...perate at minimum capacity Block 60 Incorrect parameter setting of the minimum or maximum power Block 67 A DT has been detected between flow and return sensor whereas the burner is not in operation After the DT has disappeared the block will disappear Block 80 Maximum flue gas temperature has been exceeded if present The block will not be cancelled until the flue gas temperature has arrived below ...

Страница 30: ...Installation instructions E SHR series page 30 18 CE Certificate United Kingdom ...

Страница 31: ...Installation instructions E SHR series page 31 19 CE Certificate Ireland ...

Страница 32: ...This renewed publication cancels all previous installation instructions The company reserves the right to change the specifications and dimensions without prior notice E O E ...

Отзывы: