Set-up operation
Check list
Check installation
· Is the power supply to the peripherals secured?
· Are all peripherals, escape door strikes and contacts connected?
· Is the bus line connected to the peripherals?
· Is the power supply connected to the controller?
· Is the bus line connected to the controller?
Check the settings on the 970 TSB Controller and peripherals
· Have the system settings been configured?
· Are all peripherals set to
Bus operation
?
· Has each peripheral been assigned a peripheral address?
Turning on the system
Initial operation of peripheral devices
1 Switch on the power supply to each individual peripheral.
2 Check each individual peripheral at its installation location to verify that it is
fully functional.
3 There must be no alarm active on peripherals once they are checked. If an
alarm is active, it must first be switched off and the cause of the alarm
eliminated before continuing.
Initial operation of the
970
TSB Controller
1 Turn on the power supply.
After switching on, the operating status is signalled via the LEDs (“LED
signalling”, page 15).
2 Switch on your PC and make the required settings in
FT Manager
.
Inspecting
Commissioning
Set-up operation
Содержание effeff 970-TSBC-30-10
Страница 1: ...www assaabloy com de D0134300 User manual TSB Controller 970 TSBC 30 10 Escape route technology...
Страница 19: ...19 EN Set up operation Fig 4 Configuring the network connection 1 4 3 2 1 5 7 7 6...
Страница 21: ...21 EN Set up operation Fig 5 Note on the safety certificate 1 Fig 6 Start interface of the FT Manager...
Страница 27: ...27 EN...