9
2. Installation and Setup
Unpacking
Remove the packaging.
The folder containing documentation must accompany
the
Slop Hopper
when it is delivered.
+
Before installing the
Slop Hopper
, check it for
damage in transit.
Installation
Carry out the installation in the following order:
1. Measure up and drill the holes for securing the
machine to the wall.
2. Fit the trap to the waste outlet. The trap can be
connected towards the rear or downwards.The pipe
diameter is 75mm.
3. Position the
Slop Hopper
and level it with a spirit
level held vertically against the side of the machine.
4. Fix the
Slop Hopper
to the wall. Use suitable
screws and washers for the material of the wall.
+
The wall finish must be smooth, non absorbent
and easy to clean.
5. Apply a silicone bead around the outer edge and
floor of the
Slop Hopper
.
6. Connect the water supplies. The connections must
satisfy the requirements for water connection in
accordance with the table below:
+
The pipes must be fitted with an approved ½”
shutoff valve. Seal all connections with PTFE tape.
7. Carry out the electrical installation as follows:
• Install the
Slop Hopper
in accordance with
installation category CAT II.
• If it is necessary to pass the electrical cables
through the
Slop Hopper
casing, drill a slot to
accept the 15mm inner sleeve of the grommet.
Fit the grommet and pull the cables through.
• Connect the
Slop Hopper
to a separate isolator
switch approved to local standards.
+
The isolator switch must be mounted on the
wall close to the machine.
Water
Connection
Pressure
Flow Rate
Temperature
Mains water
(Blue)
15mm (½”)
Maximum
1000 kPa
20 l/min at 400
kPa pressure
3 - 25°C