Installation Procedures
Step 5 - Connecting APsystems Microinverters to the PV Module.
Place the PV modules into position on the racking and connect the DC input
cables to the microinverters based on optimum layout configuration (up to
four PV modules per microinverter).
Figure 6
WARNING:
Double check to make sure all of the AC and DC wiring
has been correctly installed. Ensure that none of the AC and/or DC
wires are pinched or damaged. Make sure that all of the junction
boxes are properly closed.
Step 6 - Install a protective end cap at the end of AC bus cable.
b. Insert the cable end into the gasket clamp.
c. Insert five wires into five cable clamps
d. Rotate the nut with 2.5N·m until
the latching mechanism meets the base.
Figure 7
Nut
Gaske
Clamp
Seal