Section 2. Installation
Introduction
This section provides recommendations and procedures for inspecting, installing,
and testing the power supply.
Basic Setup Procedure
Table 2.1
Basic Setup Procedure
Initial Inspection
Verify that the power supply was shipped with an IEC power cord set appropriate to
the destination country and an operating manual. When you first receive your unit,
perform a quick physical check.
1. Inspect the unit for scratches and cracks, broken switches, connectors, terminals,
and missing accessories.
2. Have a service technician check the unit if you suspect internal damage.
If the unit is damaged, save all packing materials and notify the carrier immediately.
Periodic
Cleaning
No routine servicing of the power supply is required except for periodic cleaning.
Whenever a unit is removed from operation, clean the outside surfaces with a weak
solution of soap and water. If required, use low-pressure compressed air to blow dust
from in and around components on the printed circuit boards.
Step#
Description
Action
Reference
1
Inspection
Perform an initial physical
inspection of the supply.
“Initial Inspection” on page 21
2
Installation
Install the supply and ensure
adequate ventilation.
“Location and Ventilation” on
page 22
3
Test
Perform functional tests for
voltage mode operation,
current mode operation, and
front panel controls.
“Functional Tests” on page 23
Содержание Sorensen XT Series
Страница 1: ...TM XTOP 01XN Rev C www programmablepower com XT Series Programmable DC Power Supply Operation Manual...
Страница 2: ......
Страница 4: ...This page intentionally left blank ii...
Страница 6: ...This page intentionally left blank iv...
Страница 8: ...This page intentionally left blank vi...
Страница 10: ...viii...
Страница 22: ...Features and Specifications Chassis Dimensions and Weight 20 Operating Manual for XT Series Power Supply...