HYC_50 Installation and commissioning
Page 43 of 76
All rights reserved. Reproduction of this document, in whole or in part, is only permitted with the permission of alpitronic GmbH.
4.4. Commissioning protocol
During commissioning, the following protocol can be used, which contains the most
important checkpoints:
Masterdata:
Customer
Customer Column ID (EVSE-ID)
Column serial number
Maximum input power available at
the site (kW)
LoadManagement available
☐
Yes
Manufacturer/Model:
Locking cylinder
☐
alpitronic
☐
Customer, description:
Location type
☐
public
☐
private
Column address
GPS coordinates
latitude:
longitude:
Installation company
Name technician
Date of commissioning
Existing charging outlets (please tick):
1
2
CCS2_150A
CHAdeMO_125A
GB/T
CCS1
Checks before first switch-on:
Check
Executed
Result
External visual inspection of the charging pole
(damage, defects, protection class)
☐
☐
OK
☐
deficient
Checking the stability
☐
☐
OK
☐
deficient
Is the charging pole accessible?
☐
☐
OK
☐
deficient
Checking the cable connections
☐
☐
OK
☐
deficient
Check of the fuses
☐
☐
OK
☐
deficient
Visual inspection of the screw connections
(sealing wax present?)
☐
☐
OK
☐
deficient
Remove and reinsert SIM cards
☐
☐
OK
☐
deficient
Is the interior of the charging pole clean and free
☐
☐
OK
☐
deficient