Rockwell Automation Publication 750-IN020D-EN-P - May 2017
PowerFlex 755 IP00, NEMA/UL Open Type Drive
Overview
Selecting and Integrating an IP00 System
The following steps will guide you in planning and installing a PowerFlex 755
IP00, NEMA/UL Open Type drive.
1. Considerations
•
Drive size (Hp & V AC), required accessories/options (HIM, comms, etc.)
•
Ingress protection of system
•
Mounting orientation of drive
•
Cooling method, venting orientation, alignment of venting
•
Control pod mounting location
•
Cabling entry/exit scheme and cable routing provisions
•
Roll-out cart required
•
Personnel safety and necessary tooling
2. Selection
•
Select and purchase enclosure with sub-panel and ingress accessories (page
•
Select and purchase drive and corresponding drive options (see
•
Select and purchase pod and corresponding cables (page
or page
•
Select and purchase field termination kits (page
or page
)
•
Select and purchase appropriate mounting kits (drive mounting & floor - page
•
Select and purchase door fans (pages
)
•
Select and purchase necessary wire and cabling (pages
&
3. Prepare the Enclosure
•
Create ventilation openings, mount door fans (pages
)
•
Provisions for accessories (HIM cradle, etc. - see
•
Fabricate and mount inlet and outlet plenums (pages
)
•
Drill sub-panel(s) (page
& page
•
Mount field termination kit, mounting brackets, and floor kit (page
& page
•
Mounting of customer specified accessories
•
Remote mounting of control pod (if specified - see
)
•
Mount sub-panel(s)
4. Power and Ground Wiring
•
Ensure proper grounding (page
•
Position & secure movable L-brackets (page
•
Properly terminate power cables (page
•
Attach power cabling (page
5. Roll-in and Secure the Drive Unit
•
Raise drive unit to vertical orientation (page
)
•
•
Lift drive unit onto cart (see
)
•
Roll drive unit into cabinet and secure (see
6. Control Wiring
•
Mount control pod into drive (if specified - page
•
Verify control transformer voltage (page
)
•
Ensure proper cable routing (page
•
Attach pod power and fiber optic cables (page
)
•
Install real time clock battery and HIM cable (page
•
Install remaining control wiring (pages
•
Verify correct torque on all fasteners and connectors
7. Commission the System