Publication 2100-IN012B-EN-P - April 2005
2-2
Installation Procedures
Figure 2.1 Height Planning Dimensions
Securing a Motor Control
Center
Anchor bolts (1/2” [13 mm]) may be pre-located and embedded in the
foundation prior to installation. Two bolts per vertical section fasten the motor
control center through its internal mounting angle to the foundation (corner
sections require three bolts and 40” [1016 mm] wide sections require four
bolts). See Figure 2.2 through Figure 2.6 for general dimensions. Dimensions
matching your equipment can be found on the elevation drawings shipped
with your MCC.
HEIGHT OF
HANDLE
6' 7" MAX
FLOOR LINE
CEMENT PAD
Содержание CENTERLINE
Страница 1: ...CENTERLINE Low Voltage Motor Control Centers Instruction Manual ...
Страница 6: ...Publication 2100 IN012B EN P April 2005 iv ...
Страница 8: ...Publication 2100 IN012B EN P April 2005 vi ...
Страница 30: ...Publication 2100 IN012B EN P April 2005 2 10 Installation Procedures ...
Страница 42: ...Publication 2100 IN012B EN P April 2005 3 12 Final Checklist Before Energizing ...
Страница 48: ...Publication 2100 IN012B EN P April 2005 4 6 Installing Conduit and Cable ...
Страница 56: ...Publication 2100 IN012B EN P April 2005 5 8 Installing and Removing Plug In Units ...
Страница 68: ...Publication 2100 IN012B EN P April 2005 7 10 Operator Handle and Unit Interlock ...
Страница 76: ...Publication 2100 IN012B EN P April 2005 9 6 Maintenance ...
Страница 78: ...Publication 2100 IN012B EN P April 2005 10 2 Maintenance After Fault Condition ...
Страница 80: ...Publication 2100 IN012B EN P April 2005 11 2 Renewal Parts ...
Страница 85: ...Publication 2100 IN012B EN P April 2005 Parts Illustrations 12 5 Notes ...
Страница 86: ...Publication 2100 IN012B EN P April 2005 12 6 Parts Illustrations Notes ...