Installation
2
Unpacking
2.1
•
Remove the transport packaging and check that the product has not been damaged
in transit and that the consignment agrees with the specifications.
•
When lifting the unit take care not to apply stress to pipes and heat exchanger as this
may weaken them. Avoid lifting the unit by holding the heat exchanger.
Note
: Risk of injury lifting heavy objects.
Preparation
2.2
•
AL Mini City must be placed on a wall, in upright position. Use screws or bolts
suitable for the material of the wall and for the weight of the unit.
•
Choose a suitable installation area in accordance with official regulations.
The substation may generate sounds during operation caused by pumps, regulators
systems, flows etc. This should be taken in consideration during installation of the unit
so that possible operational sounds affect the surroundings as little as possible.
•
Alfa Laval recommends that the substation is mounted on well-insulated walls, such
as outer walls or on concrete walls.
•
Check the applicable regulations of the primary heating supplier.
The available differential pressure should be at least 50 kPa and at most 600 kPa.
•
Where the differential pressure is higher, a differential pressure controller should be
added to the installation.
Mounting the first fix-jig
2.3
•
Mount the first-fix-jig on the wall with two screws.
Make sure that there is enough space above for the substation and below for the
expansion vessel.
Alfa Laval recommends having 900mm from floor to upper edge of the first fix-jig.
•
Close all valves.
•
Connect the pipe work to the first fix-jig connection points.
The temperature and the pressure of the primary heating water are very
high.
Only qualified technicians
are allowed to work with the substation.
Incorrect operation may cause serious personal injury and result in
damage to the building.
•
The pipes can be pressure tested before installing the substation.
Mounting the substation
2.4
•
Before mounting the substation tighten the pipe connection
Heating network media,
supply
and
Heating network media, return
with 45Nm.
•
Remove the caps on the valves and lift up the substation. Let the frame rest on the
first fix-jig.
Содержание Mini City F2
Страница 1: ...DOC 1380 2016 15 Installation and operating Alfa Laval Mini City EN NL SV FR...
Страница 2: ......
Страница 24: ...Alfa Laval Mini City Installation and operating 24 Electrical connections...
Страница 26: ...Alfa Laval Mini City Installation and operating 26 Declaration of conformity...