Step 5: Wiring and Piggyback Plug Connections

Step 6: Testing

The wiring diagram shows eight terminals on the quick snap terminal 

blocks that consists of four pairs of connections. Make sure to read and 

review the connector examples in step 4 for proper installation prior to 

wiring.

 

Note: The quick snap terminal blocks, are herein referred to as “terminal” 

for instruction purposes. The installation example shown is for 120VAC, 

for 240VAC installation the neutral (N) wire would be replaced by line 

connection (L2) and white wire would include a red band to indicate the 

wire is hot.

  1) The  first  cable  grip,  starting  at  the  right,  has  a  cable  grip  divider 

    allowing for two power sources to be brought into the enclosure. The 

    right side of the cable grip is used for the pump power (attached in 

    series). The line wire is connected to terminal 7 and neutral wire is 

    terminated by the two-position Wago connector. The left side of the 

    cable grip is used for the alarm power, which is connected to 

    terminals 5 and 6. Terminal 5 is the neutral (N) connection and 

    terminal 6 is the line connection (L1). The pump and alarm power 

    ground wires are terminated using the three-position Wago 

    connector. After bringing in the cables, firmly tighten the cable grip 

    by twisting clockwise until securely fastened.

  2) The female receptacle comes pre-installed in the middle cable grip. 

    The line wire is connected to terminal 8, neutral wire is terminated by 

    the two-position Wago connector, and ground wire is terminated by 

    the three-position Wago connector.

  3) The third cable grip has a cable grip divider allowing for two sensor 

    connections. The filter switch is connected to terminals 1 and 2. The 

    high level alarm float switch is connected to terminals 3 and 4. After 

    bringing  in  the  cables,  firmly  tighten  the  cable  grip  by  twisting 

    clockwise until securely fastened.

  4) NEVER leave ground wire(s) exposed, use provided Wago 

    connector for wire termination.

(120VAC Example Shown)

5B

5A

PIGGYBACK PLUG CONNECTIONS

  1) Plug the male end of the piggyback plug on the pump switch power 

    cable into the pre-installed female power receptacle inside the post (5A).

  2) Plug the male end of the pump power cable into the female end of 

    the piggyback plug on the pump switch power cable (5B) from #1.

Alarm Wiring

(step 3)

Filter Switch

Alarm Float Switch

1
2
3
4

Make sure all steps of the installation and wiring process is completed 

and there is power to the product.

1) TEST ALARM LEDs and BUZZER

Press the test/silence pushbutton, lifetime pump run event counter 

statistic should display, then alarm LEDs should illuminate while 

cycling between red, green, blue, and off. The OLED screen should 

display a TESTING (COLOR) event for respective LEDs after the event 

statistic is displayed. Last, the buzzer should annunciate and OLED 

screen should display a TESTING BUZZER event.

2) TEST ALARM FLOAT SWITCH

Activate  the  alarm  float  switch,  the  red  LEDs  should  illuminate, 

flashing and the buzzer should annunciate. The OLED screen should 

display a HIGH LEVEL ALARM event.

3) TEST ALARM SILENCE

Press the test/silence pushbutton on the front of the enclosure while 

the alarm float switch is activated. The red LEDs should keep flashing 

and the buzzer should silence.

4) TEST FILTER SWITCH

Activate the filter switch, the amber LEDs should illuminate, flashing 

and the buzzer should annunciate. The OLED screen should display a 

FILTER ALARM event.

5) TEST PUMP AND PUMP FLOAT SWITCH

Make sure the tank has water to perform the testing. Activate the pump 

float  switch,  the  blue  LEDs  should  illuminate  and  the  OLED  screen 

should display a PUMP RUN event and the pump amps are displayed.

6) RECOMMENDED SYSTEM SETTINGS

Alderon™ recommends changing the factory settings for: high amp 

level, extended pump run time, and gallons per minute.

7) TEST WEEKLY

To ensure the product is functioning properly, test once a week.

Step 7: Install Bottom Cover

Line up the bottom enclosure cover with the grooves (7A), then slide 

directly upward (7B) until it meets the top of the enclosure so the screw 

hole is lined up and replace the screw at the bottom of enclosure.

Step 8: Backfill

Make sure all steps of the installation, 

wiring, and testing are complete. Take 

the dirt/soil removed and backfill the 

area for the post, riser, and direct 

burial power wiring.

Backfill 

Area

Backfill 

Area

7A

7B

B

LAC

K

B

L

AC

K

B

L

AC

K

BL

AC

K

WAGO

WAGO

G

R

O

U

ND

W

H

IT

E

/RE

D

W

H

ITE

WH

ITE

/RE

D

W

H

ITE

B

LAC

K

W

H

ITE

GROUND

5
6
7
8

1
2
3
4

Power Wiring

(steps 1 and 2)

Alarm Power
Pump Power

5
6

7

8

Factory Wired

N/L2

L1