P a g e
b.
Motor to Conveyor Shaft Drive
Chains-
Adjust the chain tension for
the sprocket assembly which
transmits power to the conveyor
shaft by loosening the pillow block
bearing bolts and sliding the shaft
and bearings in the desired
direction. Then torque the 3/8-16
Pillow Block Bolts back to 236 Inch-
Pounds (20 Foot-Pounds) when
finished. See Figure 16.
NOTE: Be
sure to maintain the horizontal
alignment of the shafts to the
chains. Failure to do so could result
in damage to the sprockets, motor,
shafts, and chains.
Figure 16.
c.
Motor to Spinner Shaft Drive
Chain
-Correct tension for the
Drive Chain is also a 5/16”
deflection at the mid-point
between the two sprockets.
Adjust the chain by loosening
the Pillow Block Bolts as was
shown in Figures 11 and 12 and
slide the pillow blocks in the
desired direction.
6.
Empty the spreader of all snow
control material when not in use to
prevent a frozen feed chain.
7.
Wash out the spreader when it is
not in use and at the end of the
season to remove all snow control
materials. Thoroughly dry all metal
surfaces. Paint and oil all bare
carbon steel surfaces to help protect
against rust build-up. Properly store
spreader during the off-seasons.
Содержание PSV-8L
Страница 10: ...OPERATORS MANUAL PSV 8L ELECTRIC AIR FLO MANUFACTURING CO INC 9 P a g e Part List Spinner Chute Assembly ...
Страница 13: ...OPERATORS MANUAL PSV 8L ELECTRIC AIR FLO MANUFACTURING CO INC 12 P a g e ...
Страница 14: ...OPERATORS MANUAL PSV 8L ELECTRIC AIR FLO MANUFACTURING CO INC 13 P a g e Chute Body with 12 Inch Extension ...
Страница 15: ...OPERATORS MANUAL PSV 8L ELECTRIC AIR FLO MANUFACTURING CO INC 14 P a g e Hopper Assembly ...