14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL
28
2. Vacuum Dry and Leakage Checking
2.1 Vacuum Dry:
use vacuum pump to change the moisture (liquid) into steam (gas) in the pipe and
discharge it out of the pipe to make the pipe dry. Under one atmospheric pressure, the boiling point of
water (steam temperature) is 212°F. Use vacuum pump to make the pressure in the pipe near vacuum
state, the boiling point of water falls relatively. When it falls under outdoor temperature, the moisture in
the pipe will be vaporized.
2.2 Vacuum dry procedure
There are two methods of vacuum dry due to different construction environment: common vacuum dry,
special vacuum dry.
①
. Common vacuum dry procedure
⚫
Vacuum dry (for the first time) ---connect the all-purpose detector to the inlet of liquid pipe and gas pipe,
and run the vacuum pump more than two hours (the vacuum pump should be below -755mmHg)
⚫
If the pump cannot achieve below -755mmHg after pumping 2 hours, moisture or leakage point will still
exist in the pipe. At this time, it should be pumped 1 hour more.
⚫
If the pump cannot achieve -755mmHg after pumping 3 hours, please check if there are some leakage
points.
⚫
Vacuum placement test: place 1 hour when it achieves -755mmHg, pass if the vacuum watch shows no
rising. If it rises, it shows there’s moisture or leakage point.
⚫
Vacuuming from liquid pipe and gas pipe at the same time.
⚫
Sketch map of common vacuum dry procedure.
Содержание ACTC1814NG1-D
Страница 4: ...14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL 2 Nomenclature...
Страница 15: ...14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL 13 60K...
Страница 23: ...14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL 21...
Страница 41: ...14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL 39 3 7 High pressure alarm 3 8 T3 High temperature protection...
Страница 42: ...14SEER AIR COOLING ONLY SYSTEM TECHNICAL MANUAL 40 3 9 High exhaust temperature protection...