3.2 Before installation
3.2.1 Installation tools
Detailed list of the tools required for installation:
No.
Installation tool
Instruction
1
Marking pen
Mark the installation hole
2
Electrodrill
Drill in the bracket or wall
3
Hammer
Hammer on the expansion bolts
4
Monkey wrench
Fix the installation bracket
5
Allen driver
Fasten the screws, remove and install AC wiring box
6
Straight screwdriver
For AC wiring
7
Megger
Measuring insulation performance and impedance
8
Multimeter
Check the circuit and AC and DC voltage
9
Electric iron
Weld communications cable
Table 7: Required installation tools
3.2.2 Installation place
Select the installation place based on the following considerations:
1.
Height from ground level should be enough to ensure that display and status LEDs are easy to read.
2.
Select a well ventilated place sheltered from direct sun radiation and rain.
3.
Allow sufficient space around the inverter to enable easy installation and removal from the mounting
surface. Please refer to Figure 8.
4.
The environment temperature should range between -25°C~60°C
.
5.
The installation position should be such that interference from other electrical devices is avoided.
6.
The inverter needs to be installed on a firm and sturdy surface, such as a wall, or metal brackets.
7.
The installation surface should be perpendicular to the horizontal line. Please refer to Figure 9