800-357-104-01, Revision 01
Before You Begin
HMS-357 List 4 and List 5
September 29, 2000
3
B
EFORE
Y
OU
B
EGIN
Prior to installing the Soneplex WBS-3190, it is important to prepare for the installation by
•
Reviewing installation plans through establishing a Method of Procedure
•
Unpacking and inspecting the system components, and
•
Gathering the tools for the installation
R
EVIEWING
I
NSTALLATION
P
LANS
Installation personnel, engineers, and Central Office (CO) supervisors, involved in the installation of the
HMS-357, should participate in the preparation of a Method of Procedure (MOP) for approval by CO
management.
E
STABLISHING
A
M
ETHOD
OF
P
ROCEDURE
Following is a list of tasks and considerations that need to be addressed and mutually agreed upon before
proceeding with installation:
•
Assignment of personnel
•
Installation tools and methods
•
Protection requirements for personnel, equipment, and tools
•
Evaluation of potential hazards that may affect service
•
Scheduled time for installation
•
Space requirements (see
“Power Requirements” on page 81
)
•
Power requirements (see
“Power Requirements” on page 81
)
•
Identification of procedures and tests required before connecting to working equipment
•
Identification of work steps and any necessary notifications to CO personnel or engineers before work begins
•
Assignment of individual system IDs for up to 32 managed systems
(see
“Setting the Shelf Identifier (Option D)” on page 30
•
Assignment of IP addresses for each installed system
(see