We suggest attaching the swing hooks before lifting the beam up onto the frame. Attach the swing
beam (part B) to your desired upright of the tower, using (part 6) nut and washer. The Nut &
Washer should sit in the recessed hole.
Two people are needed for this next bit. Lift the A-Frame into the previously dug holes. One
person holds this in place whilst the other lifts up the swing beam (part B) above the height of the
A frame. Then slowly lower the beam so it sits in between both parts A. Now check that the beam
is level and adjust the height by either digging the holes deeper or adding soil to the hole. Make
sure the A frame is upright and approximately 100cm in from the end of the beam before
continuing.
TIP: When you come to build the swing arm we
suggest you first drill a 4mm pilot hole in the two
uprights (A) before attaching the swing arm beam
B with the two 6x120mm screws.
Components & Hardware:
1 x (B) 9x9/360cm
2 x (D) 30x65/40cm
6 x (2) M10 Washers
11 x (3) M10 nuts
6 x (4) 5x60mm Screws
1 x (5) 10x150mm Bolts
2 x (6) 6x120mm Screws
5 x (7) Swing Hook