12
| XSERIES G5 START UP GUIDE | 2106001MNAA
2
Basic hardware installation
The
XFC and XRC
can be pipe-mounted, wall-mounted, or direct-mounted
to the meter run.
IMPORTANT NOTE:
Do not direct mount the larger enclosures (for
XFC – 6713, 6714 and for XRC - 6790, 6890, 6895).
Required tools and materials
To perform installations and tests, the following tools and materials are
required:
Pipe mount installation:
One (1) enclosure mounting kit (includes instructions, brackets, U-bolts
and fastening hardware)
One (1) pipe saddle with mounting hardware (size determined by
technician)
One (1) 2 inch x 40 inch pipe (length may be extended if mounting a
EFM plus bolts and washers
5 valve manifold
2 stabilizers (futbols) plus bolts and washers
Wall mount installation:
One (1) enclosure mounting kit (includes instructions, brackets, U-bolts
and fastening hardware)
Four (4) wall fasteners (length and girth determined by technician
based on wall thickness and materials)
EFM plus bolts and washers
5 valve manifold
Direct mount installation:
One (1) enclosure mounting kit (includes instructions, brackets, U-bolts
and fastening hardware)
Install input lines and manifold:
Stainless steel tubing (length determined by technician)
Four (4) sets of tube fittings, including ferrule and nut pairs
One (1) manifold (3-valve or 5-valve manifold, determined by
technician)
Leak-test manifold and tubing connections:
Liquid leak detector