2 Installation and commissioning
2.6.8. Installation of cooling fan for motors, axes 1 and 2 (option)
3HAC026876-001 Revision: F
92
© Copyri
ght
200
7-2010 ABB.
All rights reserved.
Separate cabling for axis 1 or 2
The figure below shows the cabling used only for the fan on axis 1 or 2.
xx0500002173
Installation, separate fan cabling axis 1 or 2
The procedure below details how to install the separate cabling for the cooling fan of axis 1
or 2.
4. Fit the parts of the fanbox to the motor and reassemble with
the nine attachment screws.
5. Lift the box (axis 1) so that it does not rest directly on the robot
and secure the box with the three tightening screws, using
locking liquid. Tighten them properly so that the box is firmly
attached to the motor.
6. Install the cabling and make adjustments in RobotWare, as
described in the following procedures.
Action
Note
A
Cable bracket
B
Connector R1.SW2/3, connected to the robot base
C
Connector R3.FAN2, connected to the fan of axis 1or 2
Action
Note
1. Move the robot to its calibration position.
Shown in section
and correct axis position on page
390
.
2.
DANGER!
Turn off all electric power, hydraulic and pneumatic
pressure supplies to the robot!
For Foundry Prime robots:
Do not turn off the air pressure to motors and SMB.
3. Remove the rear cover plate from the robot base. Shown in the figure
.
4. Remove the cable bracket (A)
Shown in the figure
cabling for axis 1 or 2 on page 92
Continued
Continues on next page
Содержание IRB 6640
Страница 2: ......
Страница 16: ...How to read the product manual 3HAC026876 001 Revision F 14 Copyright 2007 2010 ABB All rights reserved ...
Страница 438: ...4363HAC026876 001 Revision F Copyright 2007 2010 ABB All rights reserved ...
Страница 439: ......
Страница 440: ...ABB Robotics S 721 68 VÄSTERÅS SWEDEN Telephone 46 0 21 344000 3HAC 026876 001 Revision F en ...