10
G R I DS H I E LD
®
3 P/3 S P R ECLOS E R
3.2.1 GridShield
®
3P (single-tank recloser)
The GridShield 3P recloser is equipped with two
brackets that can be attached to its sides. These
brackets serve as a means to lift the recloser.
It is strongly recommended to use a four-point lift,
using the loops provided in these brackets (refer
to figure 1). If the unit is shipped unassembled,
you will find these brackets in one of the shipping
boxes. If the substation frames are shipped already
assembled, carefully lift the frame off the pallet,
being cautious not to cause any damage to the
poles. Then, position the frame at the desired
location. Afterward, detach the lifting brackets
from the frame and attach them to the recloser
for lifting purposes. It is important to avoid placing
the recloser on an uneven surface to prevent any
potential damage to the open/close indicators.
—
01
—
01 Lifting a GridShield
3P single-tank recloser
—
02 Lifting GridShield
3SP recloser
(compact frame)
—
03 Lifting GridShield
3SP recloser
(substation frame)
—
04 Lifting GridShield
3SP recloser (cross-
arm frame)
03
—
02
—
03
3.2.2 GridShield 3SP (three individual poles)
To ensure proper installation of a 3SP recloser,
follow these guidelines:
1. Lift the site-ready unit using either four-point
lifting points (for compact frame) or the center
lifting point (for cross-arm frame).
2. If you're dealing with individual poles, you can
use lifting straps. Alternatively, for a wrap-
around frame, lifting straps can also be used.
3. Refer to the illustrations below for visual
representation.
—
04
Содержание GridShield 3P
Страница 1: ... DISTRIBUTION SOLUTIONS GridShield 3P 3SP recloser Installation operations and maintenance manual ...
Страница 2: ......
Страница 4: ... GridShield 3P 3SP recloser ...
Страница 27: ...27 INSTALL ATION 8 2 2 Substation mount recloser grounding 36 GridShield 3P substation mount grounding 36 0 8 ...
Страница 39: ...IMPORTANT SAFET Y NOTES AND WARNINGS 39 ...