1.  Before beginning the installation, ensure that 

you have all necessary components:

• Switchgear sections
• Fastener hardware to connect sections
• Shipping split connection hardware

2.  Check that all components are in good condition. 

If there is any evidence of damage to the 
equipment, contact an ABB representative to 
evaluate the condition of the equipment before 
proceeding with installation.

3.  Carefully review all supplied project drawings 

and notes to familiarize yourself with the layout 
and construction of the switchgear.

4.  Based on the footprint shown on the general 

arrangement drawings, mark the floor for all 
drill holes necessary to fasten the switchgear 
or base frame to the floor, and for cable conduits 
(if applicable). See Fastening Sections to a 
Base Frame.

5.  Install power and secondary (control) conduits 

before moving the switchgear to the site. The 
available space for conduits appears on the floor 
plans supplied with the switchgear. Conduits 
should not extend more than 1.0 in (24 mm) 
above floor level.

Installation location requirements
The installation must meet the following 
requirements:
•  Indoor location protected from moisture and 

dramatic temperature changes. For longest 
equipment life, install the switchgear in an 
enclosed room with temperature and humidity 
control and filtered, and forced air ventilation.

•  Level the site, preferably including a base frame 

that is either embedded in the concrete floor or 
rests on a false floor on supports. The floor must 
be straight and level to +/- ¼ in (6 mm) over the 
entire length of the line-up.

•  Prepare proper openings in the floor, wall and 

ceiling for cables, conductors, pipes, bars and 
ventilation in accordance with the construction 
drawings provided.

•  Allow at least 2.5 ft (750 mm) from the top of the 

highest section to the ceiling, and at least 3.0 ft 
(920 mm) between the left and right end sections 
and the walls.

•  Allow at least 3.5 ft (1066 mm) between the unit 

and the rear wall.

Installation guidelines

Clearances – front view

Clearances – side view

•  For sections with left-mounted doors, provide at 

least 3.0 ft (920 mm) between the left wall and the 
left-end section so the doors can be opened more 
than 120°.

•  Ambient temperature is to be above -22 °F (-30 °C) 

but not exceeding 104 °F (40 °C) at 90% non-
condensing humidity. If ambient temperatures 
below 23 °F (-5 °C) will be experienced while in 
service, the manufacturer should consider addition 
of space heating or other means to help enable 
proper circuit breaker operation.

•  Allow sufficient space for future expansions, 

if required

•  Supporting brackets, beams, enclosures and 

foundation frames should be painted or treated 
with a corrosion-resistant coating. To facilitate 
installation and maintenance, the site should 
also have:

-  Convenient alignment with other equipment.
- Accessibility for maintenance.
- Adequate lighting.
-  Free access to the electrical equipment rooms.

Keep Area Free

3 ft Min.

(915 mm)

3.5 ft Min.

(1066 mm)

10 f

t M

in

.

(3

0

4

8 m

m)

12 f

t M

in

.

(3

0

4

8 m

m)

Front

Rear

3.5 ft Min.

(1066 mm)

3 ft Min.

(915 mm)

Keep Area Free

Содержание Emax Link 2 UR 1558

Страница 1: ... APPLICATION GUIDE Emax Link 2 Abbreviated Low voltage metal enclosed drawout switchgear ...

Страница 2: ...2 EMA X LINK 2 ABBREVIATED LV SWITCHGE AR APPLIC ATION GUIDE ...

Страница 3: ...13 Installation location requirements 14 Preparation 14 Section installation sequence 14 Install and connect shipping splits 14 Position shipping splits 14 Connect sections 15 Splice horizontal busbars 17 Attach switchgear to floor 17 Attach overhead lifting device 18 Raise lift device 18 Align wheels 18 Push device off the forklift 18 Operating the overhead lifting device 19 Connect cable and wir...

Страница 4: ...pping handling and installation A lineup may include more than one shipping split depending on the configuration Each vertical section is divided into several areas The instrumentation device compartment in the front of the section the bus compartment in the middle and the cable compartment for the end terminal connections at the back The front compartment within a section can be divided into smal...

Страница 5: ...A 65kA 85kA E4 2 Rated current 800A 1200A 1600A 2000A 2500A 3200A Interrupting ratings rated voltage 65kA 85kA 100kA 240V 65kA 85kA 100kA 480V 65kA 85kA 100kA 600V Rated short time current 65kA 85kA 100kA E6 2 Rated current 4000A 5000A Interrupting ratings rated voltage 85kA 100kA 240V 85kA 100kA 480V 85kA 100kA 600V Rated short time current 85kA 100kA Environmental conditions Enclosure rating NEM...

Страница 6: ...osed in a covering to protect them from atmospheric conditions during shipment however the covering is not suitable for storage outdoors For instructions regarding the various components refer to the manual associated with each product Crate dimensions H x W x D Number of sections in shipping block By selection width Section depth 72 84 One 18 22 30 24 X 78 28 X 78 36 X 78 24 X 90 28 X 90 36 X 90 ...

Страница 7: ...631 kgs 5000A 38 0 in 965 mm 2207 lbs 1002 kgs 2344 lbs 1064 kgs Main Tie Main section 1200A 18 0 in 457 mm 1314 lbs 597 kgs 1340 lbs 608 kgs 2000A 22 0 in 559 mm 1807 lbs 820 kgs 1831 lbs 831 kgs 3200A 30 0 in 762 mm 2408 lbs 1093 kgs 2442 lbs 1109 kgs 5000A 38 0 in 965 mm 3663 lbs 1663 kgs 3800 lbs 1725 kgs Feeder section 3x1200A 18 0 in 457 mm 1375 lbs 624 kgs 1401 lbs 636 kgs 3x2000A 22 0 in 5...

Страница 8: ...m the top bottom and sides of the equipment Lifting angles are provided to allow lifting by crane Cubicle device label Each cubicle and device are prominently labeled to display approval agency marking Section arrangement Vertical sections are composed of the following three main compartments 1 Device compartment Composed of up to four vertical locations that house the installed devices which are ...

Страница 9: ... various configurations depending on the current rating Horizontal busbars Bus phases The horizontal busbar is located at the bottom of each section The phase arrangement of 3 phase horizontal busbar and vertical busbars is A B C from top to bottom or left to right as viewed from the front The busbar systems are installed in the lower level busbar compartment The tie busing will be installed at th...

Страница 10: ...al tin plated copper Bus ratings and sizes Horizontal neutral bus optional feature When required a 100 rated neutral horizontal busbar is provided in the busbar compartment above the lower A phase horizontal busbar For 4 wire systems that have no line to neutral load requirements an incoming neutral connection point can be provided to facilitate the power system grounding connection but without ne...

Страница 11: ...e switches In addition to the standard items listed above instrument compartments may also include ammeters voltmeters high resistance grounds HRGs potential transformers and relays These instruments can be installed inside the compartments or on the front of the instrument compartment door Section and location numbering Each section is sequentially numbered as the general arrangement drawings are...

Страница 12: ... accessibility Cable compartment may have an optional cable support structure which is adjustable in vertical and horizontal position Top horizontal wireway The Top wireway provides the space for interconnection wiring and is covered by a steel hinged door secured by a bolted cover Top horizontal wireway Bottom horizontal wireway The bottom horizontal wireway is covered by a steel bolted cover and...

Страница 13: ...se frame that is either embedded in the concrete floor or rests on a false floor on supports The floor must be straight and level to in 6 mm over the entire length of the line up Prepare proper openings in the floor wall and ceiling for cables conductors pipes bars and ventilation in accordance with the construction drawings provided Allow at least 2 5 ft 750 mm from the top of the highest section...

Страница 14: ...able on the horizontal bussing Install and connect shipping splits Note Diagrams showing the location of fasteners and the appropriate torque values are included in the Torque Table section of this manual Installation guidelines Position shipping splits Remove the shipping splits from their pallets or skids If you need to support a multiple section shipping split at the base after removing it from...

Страница 15: ...A and on the left hand side for phases B and C of each section Slide the splice links to the right or left to connect the bus to the adjacent section 1 After installing and connecting the shipping splits connect the main horizontal bus splice links and tighten the hardware to the specified torque Splice kits supplied from the factory are installed on the right hand side for neutral and phase A and...

Страница 16: ...if provided You must splice the horizontal ground bus between adjacent sections in the cable compartment Splice links are provided on the right hand side of each section for neutral and Phase A and on the left hand side for Phases B C and the ground The links may be loosened and bridged to the adjacent section Note The holes at the ends of all busbars ensure adequate adjustment within the required...

Страница 17: ...tructions To attach the lifting device 1 Remove the carriage stop from one end of the lineup Remove carriage stop 2 Loosen all rails for the overhead lift device and mount the locator plates Note that the plates have round bosses that mate with holes in the rails 3 Adjust the rails as required to loosely secure the locator plates in place with the bosses in their mating holes N O I T C E S B B E L...

Страница 18: ...head lift device off the forklift onto the rails Test the continuous movement of the overhead lift device If the movement is correct reinstall the carriage stop bracket Operating the overhead lifting device Observe the following requirements when operating the circuit breaker lifting device The wheels must be properly set on track Do not depend upon the drum attachment to support the full breaker ...

Страница 19: ... phase 18 22 30 38 800 4 X1 4 NA 3 24 18 22 30 38 1200 3 X1 4 NA 3 24 18 22 30 38 1600 4 X1 4 1 3 24 18 22 30 38 2000 4 X1 4 1 3 24 E4 2 breaker connection table 1600A 3200A Section width inches Continuous current Run backs sizes Number of lamination Number of lug pad phase Number of holes per phase 18 22 30 38 800 4 X1 4 NA 3 24 18 22 30 38 1200 3 X1 4 NA 3 24 18 22 30 38 1600 4 X1 4 1 3 24 18 22...

Страница 20: ...ale 1 5 Detail B Scale 1 5 Space for Control cable Space for Power cable conduit Bottom top entry Section depth Conduit space depth Distance to bus compartment Distance between base channels A B C D 72 00 20 75 29 00 29 10 84 00 32 75 41 00 41 10 Section width Conduit space width Distance between anchor holes E F G 18 00 14 00 10 41 22 00 18 00 14 41 31 00 26 00 22 41 38 00 34 00 30 41 ...

Страница 21: ... horizontal wireway are dedicated to control wires The horizontal wireway enables running control wiring between sections Connect between horizontal and vertical wireways There are openings available between the vertical locations A B C D for control wiring Openings are 2 5 in 63 5 mm in diameter Connect control wiring between sections The device compartment segregation walls have openings to conn...

Страница 22: ...n equipment usage and the operating environment Perform a visual inspection front and rear to see that there is no evidence of loose parts warping or undue vibration Take steps to remedy any deficiencies of this nature that may appear Keep the assembly dry Cover to prevent moisture from dripping on the equipment Do not block vents Installation guidelines There are hazards of electrical shocks and ...

Страница 23: ... prone to overheating Open all hinged panels and remove all bolted panels Clean insulation thoroughly Withdraw and clean all drawout components Clean the stationary portion of the switchgear by wiping with a clean cloth Compressed dry air is useful for cleaning inaccessible areas Remove covers of all panel devices where possible Check wiring for secure connections Clean contacts on relays and swit...

Страница 24: ...max Link 2 LV switchgear torque table Union Description Screw English ft lbs Splice kit connections Breaker connections Run ins run backs to E1 2 breaker 3 8 16 33 Run ins run backs to E2 2 breaker 3 8 16 33 Run ins run backs to E4 2 breaker 1 2 13 78 Run ins run backs to E6 2 breaker 1 2 13 78 Bus bar ground connections Run ins to vertical riser 1 2 13 78 L connection to vertical riser 1 2 13 78 ...

Страница 25: ... Hex head bolt nut Torque 40 50 lb ft 1 2 13 Hex head bolt nut Torque 40 50 lb ft 3 8 16 Hex head bolt nut Torque 20 25 lb ft 3 8 16 Hex head bolt nut Torque 20 25 lb ft 1 2 13 Hex head bolt nut Torque 40 50 lb ft 1 2 13 Hex head bolt nut Torque 40 50 lb ft 1 4 20 Tread forming screw Torque 4 6 lb ft Top horizontal wireway door Top plate Lifting angles Bottom plate 1 4 20 Hex head bolt nut Torque ...

Страница 26: ...d to purchase orders the agreed particulars shall prevail ABB Inc does not accept any responsibility whatsoever for potential errors or possible lack of information in this document We reserve all rights in this document and in the subject matter and illustrations contained therein Any reproduction disclosure to third parties or utilization of its contents in whole or in parts is forbidden without...

Отзывы: