… 8 Commissioning
Checks prior to commissioning
The following points must be checked before commissioning the
device:
• Correct wiring in accordance with
Electrical connections
on page 46.
• Correct grounding of the sensor.
• The ambient conditions must meet the requirements set
out in the specification.
• The power supply must meet the requirements set out on
the name plate.
Switching on the power supply
• Switch on the power supply.
The LCD display shows the following display during the startup
process:
System Startup
Processing
The process display is displayed after the startup process.
Parameterization of the device
The CoriolisMaster FCB400, FCH400 can be commissioned and
operated via the integrated LCD indicator (see chapter
Menu:
Easy Set-up
on page 70).
Alternatively, the CoriolisMaster FCB400, FCH400 can also be
commissioned and operated via standard HART tools. These
include:
• ABB HART handheld terminal DHH805 (FCB4xx EDD)
• ABB Asset Vision Basic (FCB4xx DTM)
• ABB 800xA control system (FCB4xx DTM)
• Other tools supporting standard HART EDDs or DTMs
(FDT1.2)
Note
Not all tools and frame applications support DTMs or EDDs at
the same level. In particular, optional or advanced EDD / DTM
functions may not be available on all tools. ABB provides frame
applications supporting the full range of functions and
performance.
Installation of ABB AssetVision Basic and ABB Field
Information Manager (FIM)
There are two different software packages available for
configuration:
• ABB AssetVision Basic combined with the ABB
CoriolisMaster Device Type Manager (DTM).
• ABB Field Information Manager (FIM) combined with the
ABB CoriolisMaster Field Device Information Package (FDI
package).