Page 18

 Shutters – locked and covering primary stabs
 Breaker position label – intact and legible
 Compartment door – moves freely and has no difficulty securing when closed
 TOC switch – actuator arm moves inward and springs back outward
 Secondary terminals – secured and no loose wires

Cell Functional Testing

 Truck lift platform locking tab engages into cell compartment slot (see figure 13)
 Breaker interlocks fully engage module interlock slot (see figure 13)
 Circuit breaker racks in to “Test” with little resistance (<25lbs torque)
 Breaker locks into test position
 Circuit breaker operates in “Test” position (Open/Close) – both manually and remotely
 Breaker fails to close when charged and in an intermediate racking position – between “Test” and

“Connect”

 Circuit breaker racks in to the “Connect” position with little resistance, increasing only within ~1 inch prior

to the connect position (<50lbs torque)

 Shutter mechanism unlocks and opens – shutters unlock and begin to open between test and connect
 TOC switch – actuator arm moves inward when breaker is connected and springs back outward when

breaker is racked out

 Breaker locks into connect position
 Circuit breaker operates in “Connect“ position (Open/Close)
 Indicating lights operate as expected (Open/Close) – On some ABB Switchgear, the Breaker “Open”

indicating light serves as both the breaker is open and that the breaker has reached either the “Test” or
“Connect” position during racking. This is due to the breaker’s TOC “pin monitor” contact being in series
with the breaker “Open” indicating light circuit. The pin monitor is only closed when the breaker is in one of
the three racking positions “Disconnect”, “Test” and “Connect” and the racking pin has fully seated into
position.

 All controls function properly

Breaker has passed all inspection and operational testing.

Sign and Date _____________________________________

NOTES:

___________________________________________

_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________
_______________________________________________

Provide an electronic copy of the completed check list to:

ABB Inc.
Medium Voltage Switchgear

655 Century Point
Lake Mary, Florida 32746
Phone:                     +1 407 732 2000
Customer service:       +1 800 929 7947 ext. 5

+1 407 732 2000 ext. 5

E-Mail:  [email protected]

Courtesy of NationalSwitchgear.com

Содержание AMVAC

Страница 1: ...AMVACTM and ADVACTM Breaker commissioning procedures Courtesy of NationalSwitchgear com...

Страница 2: ...1VAL0501 MB Rev A Oct 2015 Courtesy of NationalSwitchgear com...

Страница 3: ...4 6 Racking DISCONNECT to TEST 10 4 7 In Cell Testing 11 4 8 Racking TEST to CONNECT 11 4 9 Racking CONNECT to TEST 12 4 10 Racking TEST to DISCONNECT 12 4 11 Removal 12 4 12 Standard Color 13 4 13 G...

Страница 4: ...egarding the potential hazards for themselves and other personnel in the area These instructions are intended for use by fully qualified personnel and are not a substitute for adequate training experi...

Страница 5: ...gh center of gravity into account Carry out loading operations only when it has been ensured that all precautionary measures to protect personnel and materials have been taken into consideration 3 3 S...

Страница 6: ...2 Truck mounting WARNING Always follow safe work practices when lifting the circuit breakers to protect the safety of personnel and equipment Always inspect lifting hook for signs of wear or damage be...

Страница 7: ...the lift truck facing toward the truck Figure 4 12 It may be necessary to use the racking handle to rotate the racking screw slightly left or right to free up the truck handles Figure 4 8 Lifting hook...

Страница 8: ...eaker interlock tabs must engage the slots in the lift truck platform before releasing the foot brake and moving the lift truck Lower the lift truck platform before transporting draw out modules from...

Страница 9: ...insure closed indicator is shown c Perform a manual open operation ADVAC only Note if there are any deficiencies during the operations Check the breaker s secondary power requirements listed on the f...

Страница 10: ...tential to the required voltage Figure 4 15 4 Hold for one minute 5 Decrease potential to 0 zero and turn off machine 6 Repeat for the remaining 5 terminals A successful withstand indicates satisfacto...

Страница 11: ...breaker They are a safe distance from the stationary part of the device located on the housings 2 The TEST position disengages the main disconnecting devices and engages the control contacts This posi...

Страница 12: ...ruck foot pedals or lowering the platform with the lift truck control valve Figure 4 19 to lock the locking tabs in the lift truck holding slot The truck platform should be horizontal and aligned with...

Страница 13: ...from the DISCONNECTED position to the TEST Position Press down on the racking release handle on the breaker compartment door Figure 4 22 Figure 4 22 Racking release handle 1 Engage the racking screw o...

Страница 14: ...ther or both the manual opening switch on the gear or associated breaker relay Check that the breaker is open and appropriate indicating lights are active Figure 4 24 Circuit breaker in CONNECTED posi...

Страница 15: ...must disable the UV prior to discharging the breaker 3 Align the locking tabs of the lift truck with the lift truck holding slots in the front of the frame Push the lift truck to the frame to engage...

Страница 16: ...galvanized steel Galvanized steel greatly exceeds the paint qualifications of ANSI C37 20 2 Section 5 2 8 4 14 Primary Disconnect Assemblies Circuit breaker primary disconnects consist primarily of a...

Страница 17: ...ry air vacuum or if necessary with an OSHA approved solvent 4 Check the calibration of protective relays 5 Follow the recommendations of any individual device instructions furnished for maintenance of...

Страница 18: ...or various raw materials The duty of ABB is to facilitate subsequent recycling or disposal at the end of product life During disposal of the product it is always necessary to act in accordance with lo...

Страница 19: ...nclusive or covering all contingencies No warranties expressed or implied including warranties of fitness for a particular purpose or merchantability or warranties of fitness for a particular purpose...

Страница 20: ...f needed Shutter rollers are clean straight and undamaged Truck wheels are parallel with truck sides and rotate freely Wire harness not loose or damaged Components not loose or missing Mechanism is gr...

Страница 21: ...t breaker operates in Connect position Open Close Indicating lights operate as expected Open Close On some ABB Switchgear the Breaker Open indicating light serves as both the breaker is open and that...

Страница 22: ...Page 19 Courtesy of NationalSwitchgear com...

Страница 23: ...is for general information purposes only While ABB strives to keep the information up to date and correct it makes no representations or warranties of any kind express or implied about the completene...

Отзывы: