ACX Analyzer System Commissioning Instruction
CI/ACX-EN Rev. D
Installing the Analyzer System
•
We recommend having the analyzer system installed by ABB.
•
When installing the analyzer system, in addition to this manual, comply with the
information contained in the drawings set.
•
If there is shipping damage which points to improper handling file a damage claim
with the shipper (railway, mail or freight carrier) within seven days.
•
Make sure the enclosed accessories are not lost (see the “Items Delivered” section,
page 23).
•
Keep the packaging material for future shipping needs.
Installation – Overview
Step
Action
Page
1
Prepare the gas sampling probe installation site.
15
2
Prepare the analyzer cabinet installation site.
16
3
Install the gas sampling probe and filter unit.
25
4
Install the sample gas line.
35
5
Install the back-purging unit (if applicable).
39
6
Install the analyzer cabinet.
47
7
Install the instrument air and test gas supply (if applicable).
49
8
Connect the gas lines to the analyzer cabinet.
51
9
Connect the electrical leads to the analyzer cabinet.
52